Contractor's Claims. If the Contractor wishes to make a claim for a change in the Contract Price or the Contract Time, the Contractor shall give RMWD written notice thereof within ten (10) work days after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work covered by the claim except in an emergency endangering life or property. No such claim shall be valid unless so made. Any change in the Contract Price or the Contract Time resulting from a claim that is approved by RMWD will be authorized by Change Order.