Contractor’s Notice of Delay. 16.1.1. In addition to the requirements indicated in this subsection, Contractor shall notify the District pursuant to the claims provisions in these General Conditions of any anticipated delay and its cause. 16.1.2. Contractor shall, within FIVE (5) calendar days of any delay impacting the critical path in completing the Work, notify District in writing of the causes of the delay including documentation and facts explaining the delay.
Appears in 6 contracts
Samples: Master Site Lease, Site Lease, Site Lease
Contractor’s Notice of Delay. 16.1.1. In addition to the requirements indicated in this subsection, Contractor shall notify submit any request for an adjustment of the District pursuant to Contract Price or the claims Contract Time through the Change Order provisions in these General Conditions of any anticipated delay and its causeConstruction Provisions.
16.1.2. Contractor shall, within FIVE (5) calendar days of any delay impacting the critical path in completing the Work, notify District in writing of the causes of the delay including documentation and facts explaining the delay.
Appears in 1 contract
Samples: Site Lease
Contractor’s Notice of Delay.
16.1.1. In addition to the requirements indicated in this subsection, Contractor shall notify submit any request for an adjustment of the District pursuant to Contract Price or the claims Contract Time through the Change Order provisions in these General Conditions of any anticipated delay and its causeConstruction Provisions.
16.1.2. Contractor shall, within FIVE (5) calendar days of any delay impacting the critical path in completing the Work, notify District in writing of the causes of the delay including documentation and facts explaining the delay.
Appears in 1 contract
Samples: Site Lease
Contractor’s Notice of Delay. 16.1.1. In addition to the requirements indicated in this subsection, Contractor shall notify the District pursuant to the claims provisions in these General Conditions of any anticipated delay and its cause.
16.1.2. Contractor shall, within FIVE (5) calendar days of any delay impacting the critical path in completing the Work, notify District in writing of the causes of the delay including documentation and facts explaining the delay.
16.1.3. Any request by Contractor for an adjustment of the Contract Price or the Contract Time for a
16.1.4. Any claim for delay must include the following information as support, without limitation: