Coordination of Design and Construction Contract Documents. 5.5.1 Review model(s), Drawings, Specifications and other Construction Documents as they are developed by A/E during the Schematic Design, Design Development, and Construction Documents design phases of the Project.
Appears in 45 contracts
Samples: assets.system.tamus.edu, assets.system.tamus.edu, assets.system.tamus.edu
Coordination of Design and Construction Contract Documents. 5.5.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by A/E during the Schematic Design, Design Development, and Construction Documents design phases of the Project.
Appears in 18 contracts
Samples: Agreement for Design Build Services, Agreement, assets.system.tamus.edu
Coordination of Design and Construction Contract Documents. 5.5.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by A/E the Project Architect during the Schematic Designschematic design, Design Developmentdesign development, and Construction Documents construction documents design phases of the Project.
Appears in 12 contracts
Samples: Agreement, Agreement, cdn.cocodoc.com
Coordination of Design and Construction Contract Documents. 5.5.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by Project A/E during the Schematic Designschematic design, Design Developmentdesign development, and Construction Documents construction documents design phases of the Project.
Appears in 6 contracts
Samples: Agreement Between Owner And, Agreement Between Owner And, Agreement Between Owner And
Coordination of Design and Construction Contract Documents. 5.5.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by the A/E during all the Schematic Design, Design Development, and Construction Documents different design phases of the Project.
Appears in 6 contracts
Coordination of Design and Construction Contract Documents. 5.5.1 5.1.4.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by A/E the Project Architect during the Schematic Designschematic design, Design Developmentdesign development, and Construction Documents construction document design phases stages of the Project.
Appears in 6 contracts
Samples: Agreement, Agreement, Draft Agreement
Coordination of Design and Construction Contract Documents. 5.5.1 5.1.4.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by Project A/E during the Schematic Designschematic design, Design Developmentdesign development, and Construction Documents construction document design phases stages of the Project.
Appears in 3 contracts
Samples: Agreement Between Owner and Design, Agreement Between Owner and Design, www4.mdanderson.org
Coordination of Design and Construction Contract Documents. 5.5.1 8.5.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by A/E the Project Architect during the Schematic Designschematic design, Design Developmentdesign development, and Construction Documents construction documents design phases of the Project.
Appears in 2 contracts
Samples: Professional Services Agreement, Professional Services Agreement
Coordination of Design and Construction Contract Documents. 5.5.1 Review model(s)5.1.4.1 The Design/Build Contractor shall review all drawings, Drawingsspecifications, Specifications and other Construction Documents as they are developed by Athe Project Architect/E Engineer during the Schematic Design, Design Development, and Construction Documents Document design phases stages of the Project.
Appears in 2 contracts
Coordination of Design and Construction Contract Documents. 5.5.1 Review model(s), all Drawings, Specifications Specifications, and other Construction Documents as they are developed by the A/E during all the Schematic Design, Design Development, and Construction Documents different design phases of the Project. construction feasibility, availability of labor and materials, procurement time requirements, and construction coordination.
Appears in 2 contracts
Samples: www.smartrisk.biz, gato-docs.its.txst.edu