Day Work The Company shall structure the Project Working Hours to include one (1) half-hour rest break to be taken without deduction of pay by Employees working the Project Working Hours on any day (Monday to Saturday inclusive).
Work Week and Work Day (a) (Applicable to full-time employees only) The normal or standard work week shall be an average of thirty-seven and one-half (37½) hours, with a normal or standard work day of seven and one-half (7½) hours except in those Hospitals where agreements already provide a standard or normal work week of less than thirty-seven and one-half (37½) hours per week and seven and one-half (7½) hours per day. (Those Hospitals with the lesser required hours shall reflect in the salary rates a pro-rata lesser amount compared with salaries for other Hospitals based on the ratio that the standard or normal hours of work at the Hospital concerned are to thirty-seven and one-half (37½) hours and shall appropriately reflect such hours in this Article). The length of time over which the hours of work per week are to be averaged shall be determined locally and shall be set out in the Local Provisions Appendix. (b) (applicable to part-time employees only) The normal or standard work day shall be seven and one-half (7½) hours per day and the normal or standard full- time work week shall be an average of thirty-seven and one- half (37½) hours per week except in those hospitals where agreements already provide a normal or standard work day of less than seven and one-half hours and a normal or standard full-time work week of less than thirty-seven and one-half (37½) hours. (Those Hospitals with the lesser required hours shall reflect in the salary rates a pro-rata lesser amount compared with salaries for other Hospitals based on the ratio that the standard or normal hours work at the Hospital concerned are to thirty-seven and one-half (37½) hours and shall appropriately reflect such hours in this article.) Part-time employees shall be entitled to overtime pay at the rate of time and one-half their regular straight time hourly rate for all hours worked in excess of the normal or standard work day or in excess of the normal or standard full-time work week. The length of time over which the hours of work per week are to be averaged shall be determined locally and shall be set out in the Local Provisions Appendix. (c) Where the Hospital and the Union agree, subject to the approval of the Ministry of Labour, other arrangements regarding hours of work may be entered into between parties on a local level with respect to tours beyond the normal or standard work day in accordance with the provisions set out in Article 25.01 of the collective agreement.
Work Hours Except in emergencies, the standard work week of full-time unit employees shall normally consist of five (5) days of eight (8) hours each, exclusive of lunch hour. Each employee shall be assigned regular starting and ending times, which shall not be changed without prior notice. Should an employee be required to work during his/her lunch hour, the length of such interruption shall be counted as time worked unless other arrangements are made with his/her supervisor.
Work Day and Work Week The normal work day shall consist of up to 8 hours of work within a 24-hour period. The normal work week shall consist of up to 40 hours of work within a 7-day period. The Employer may define the work week on an individual, department, shift or facility basis in accordance with Federal and State law.
Contract Schedule The information set forth in the Contract Schedule is true and correct.
Contract Work Contract work means capital project work within existing plant facilities, major maintenance and/or revamp work, plant modifications and/or shutdown work, minor maintenance and/or repair work, breakdown maintenance.
Punchlist Upon completion of the Performance Tests and prior to Substantial Completion, Owner and Contractor shall inspect Subproject 3, and Contractor shall prepare a proposed Punchlist of items identified as needing to be completed or corrected as a result of such inspection. Contractor shall promptly provide the proposed Punchlist to Owner for its review, together with an estimate of the time and cost necessary to complete or correct each Punchlist item. Contractor shall add to the proposed Punchlist any Punchlist items that are identified by Owner within ten (10) Days after Owner’s receipt of the proposed Punchlist from Contractor, and Contractor shall immediately initiate measures to complete or correct, as appropriate, any item on Contractor’s proposed Punchlist (including those items identified by Owner during Owner’s review) that are not of a Punchlist nature. Notwithstanding anything to the contrary in this Agreement, Contractor and Owner are not required as a condition of Substantial Completion to agree upon and identify every Punchlist item and include it on the Punchlist, but Contractor is required to complete as a condition of Substantial Completion all Work that does not meet the definition of Punchlist as provided in Section 1.1. In the event of a dispute regarding whether a specific item of Work meets the definition of Punchlist under Section 1.1, the Parties shall resolve such dispute in accordance with Section 18.1A. Owner shall provide Contractor with access to the Work after Substantial Completion sufficient to enable Contractor to complete all Punchlist items, so long as such access does not unreasonably interfere with operation of Subproject 3 after Substantial Completion or Subproject 1 or Subproject 2 after substantial completion of Subproject 1 or Subproject 2 (as applicable) under the Stage 1 EPC Agreement and subject to any reasonable security or safety requirements of Owner. Upon Contractor’s completion or correction of any items necessary to achieve Substantial Completion, as modified by any Owner additions, such Punchlist shall govern Contractor’s performance of the Punchlist items up to Final Completion. All Work on the Punchlist shall be completed by the date required for Final Completion, as specified in Section 5.3C, or Owner may, in addition to any other rights that it may have under this Agreement, complete such Punchlist Work at the expense of Contractor. In the event Owner elects to complete such Punchlist Work, Contractor shall pay Owner, within ten (10) Days after receipt of written notice from Owner, all reasonable costs and expenses incurred by Owner in performing such Punchlist Work, or, at Owner’s sole discretion, Owner may withhold or offset amounts owed to Contractor or collect on the Letter of Credit in accordance with Section 7.8 in the amount of such costs and expenses. Any Defective Work identified after agreement between the Parties of the Punchlist shall be corrected by Contractor as a Warranty item under Article 12.
Standard Work Week The standard work week for full-time employees covered by this Agreement shall be forty (40) hours, exclusive of the time allotted for meal periods, consisting of five (5) consecutive work days followed by two (2) consecutive days off. The week shall commence with the shift that includes 12:01 A.M. Sunday of each calendar week and end at the start of the shift that includes 12:00 midnight the following Saturday. The Employer retains the right to modify the work schedules to meet operational needs.
Work Week The work week will begin at 12:00 a.m. on Sunday and end at 11:59 p.m. the following Saturday.
Work Day The standard work day shall be eight (8) consecutive hours of work exclusive of a lunch period in a consecutive twenty-four (24) hour day.