Deductive Change Orders. All deductive Change Order(s) must be prepared pursuant to the provisions herein. If Contractor offers a proposed amount for a deductive Change Order(s), Contractor shall include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of the work of the Change Order(s). If Subcontractor work is involved, Subcontractors shall also include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of its deducted work. Any deviation from this provision shall on be permitted with the District’s prior written approval.
Appears in 7 contracts
Samples: Master Site Lease, Master Site Lease, Site Lease
Deductive Change Orders. All deductive Change Order(s) must be prepared pursuant to the provisions herein. If Contractor Developer offers a proposed amount for a deductive Change Order(s), Contractor Developer shall include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of the work of the Change Order(s). If Subcontractor work is involved, Subcontractors shall also include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of its deducted work. Any deviation from this provision shall on be permitted with the District’s prior written approval.
Appears in 5 contracts
Samples: Facilities Lease, Master Facilities Lease, Master Facilities Lease
Deductive Change Orders. All deductive Change Order(s) must be prepared pursuant to the provisions herein. If Contractor offers a proposed amount for a deductive Change Order(s), Contractor shall include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of the work of the Change Order(s). If Subcontractor work is involved, Subcontractors shall also include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of its deducted work. Any deviation from this provision shall on only be permitted with the District’s prior written approval.
Appears in 4 contracts
Samples: Site Lease, Site Lease, Site Lease
Deductive Change Orders. All deductive Change Order(s) must be prepared pursuant to the provisions herein. If Contractor offers a proposed amount for a deductive Change Order(s), Contractor shall include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of the work of the Change Order(s). If Subcontractor work is involved, Subcontractors shall also include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of its deducted work. Any deviation from this provision shall on not be permitted with without the District’s prior written approval.
Appears in 1 contract
Samples: Facilities Lease
Deductive Change Orders. All deductive Change Order(s) must be prepared pursuant to the provisions herein. If Contractor Designer/Builder offers a proposed amount for a deductive Change Order(s), Contractor Designer/Builder shall include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of the work of the Change Order(s). If Subcontractor work is involved, Subcontractors shall also include a minimum of five percent (5%) total overhead, profit & general conditions to be deducted with the amount of its deducted work. Any deviation from this provision shall on be permitted with the DistrictCustomer’s prior written approval.
Appears in 1 contract
Samples: Contract for Design and Construction