Delay Days. Delay Days shall be considered working days. Delay Days will be evaluated and identified as one of the three categories listed below. Excusable delays will create adjustments in the contract time. Compensable delays will create adjustments in both the contract sum and contract time. In the event of concurrent delays, no delay damages are recoverable by either the DISTRICT or the CONTRACTOR, but an extension in time shall be granted for each contemporaneous delay day occurring on the critical path. Contemporaneous delays shall be evaluated using a schedule fragnet(s), schedule updates, daily reports, notices, and any other records of delaying events. 1. Excusable & Compensable 2. Excusable &Non-Compensable 3. Inexcusable
Appears in 4 contracts
Samples: General Conditions, General Conditions, General Conditions