Delay, Postponement or Suspension of Work Sample Clauses

Delay, Postponement or Suspension of Work. 7.1.1 The Owner shall have the right to delay, postpone or suspend the Contract Work, or any portion thereof, immediately or upon a specified date, for a period of not more than one-hundred and twenty (120) days, upon written Notice to the Contractor and for any reason deemed by the Owner to be in its interest. The Contractor and all of its Subcontractors and Representatives shall cease all Contract Work, or any portion thereof, immediately or as of the date specified in the Notice. 7.1.2 Any such delay, postponement or suspension shall not give rise to any cause of action for damages against the Owner or the City, but the Contract Term specified in Part I of this Contract and the Contractor’s time for performance of the Contract Work shall be extended for the period of the delay, postponement or suspension. 7.1.3 In the event the Owner delays, postpones or suspends the Contract Work for more than one-hundred and twenty (120) days, the Owner, after consultation with the Contractor, may: 7.1.3.1 Terminate the Contract; or 7.1.3.2 Extend the Contract Term specified in Part I of this Contract and increase the Maximum Contract price set forth in Part I of this Contract to include any additional mobilization or other costs incurred by the Contractor as a direct result of such delay, postponement or suspension; or 7.1.3.3 Negotiate a new contract with the Contractor. 7.1.4 The Contractor shall be solely responsible for securing the Contract Work, removing or correcting all hazardous conditions and ensuring that the Work Site is made safe and maintained in a safe condition to the Owner’s satisfaction during any period of delay, postponement or suspension. 7.1.5 The Contractor shall resume the Contract Work upon the date specified in the Notice or upon such other date as the Owner may thereafter specify in writing.
AutoNDA by SimpleDocs
Delay, Postponement or Suspension of Work. 7.1.1 The Owner shall have the right to delay, postpone or suspend the Contract Work, or any portion thereof, immediately or upon a specified date, for a period of not more than one-hundred and twenty (120) days, upon written Notice to the Contractor and for any reason deemed by the Owner to be in its interest. The Contractor and all of its Subcontractors and Representatives shall cease all Contract Work, or any portion thereof, immediately or as of the date specified in the Notice. 7.1.2 Any such delay, postponement or suspension shall not give rise to any cause of action for damages against the Owner or the City, but the Contract Term specified in Part I of this Contract and the Contractor’s time for performance of the Contract Work shall be extended for the period of the delay, postponement or suspension. 7.1.3 In the event the Owner delays, postpones or suspends the Contract Work for more than one-hundred and twenty (120) days, the Owner, after consultation with the Contractor, may:
Delay, Postponement or Suspension of Work. 3.1.1 The Owner shall have the right to delay, postpone or suspend the Services, or any Portion thereof, immediately or upon a specified date, for a period of not more than ninety (90) days, upon Notice to the Consultant, for any reason deemed by the Owner to be in its interest. The Consultant and all of its Subcontractors and Representatives shall cease all Services, or any specified Portion thereof, immediately or as of the date specified in the Notice. 3.1.2 Any such delay, postponement or suspension shall not give rise to any cause of action for damages against the Owner or the City, but the Term specified in Part I of this Contract and the Consultant’s time for performance of the Services shall be extended for the period of the delay, postponement or suspension. 3.1.3 In the event of any delays, postponements or suspensions, the Consultant shall resume the Services upon the date specified in the Notice or upon such other date as the Owner may thereafter specify by Notice. Time for Consultant re-mobilization may be required prior to resuming Services. If the Project is resumed after being postponed, delayed or suspended for more than twelve (12) months, the Consultant’s Basic Compensation shall be equitably adjusted subject to approval by BBPC.

Related to Delay, Postponement or Suspension of Work

  • Suspension of Work The Department may, at its sole discretion, suspend any or all activities under the Contract, at any time, when it is in the best interest of the State of Florida to do so. The Customer may suspend a resulting contract or purchase order, at any time, when in the best interest of the Customer to do so. The Department or Customer will provide the Contractor written notice outlining the particulars of the suspension. After receiving a suspension notice, the Contractor must comply with the notice and will cease the performance of the Contract or purchase order. Suspension of work will not entitle the Contractor to any additional compensation. The Contractor will not resume performance of the Contract or purchase order until so authorized by the Department.

  • Suspension of Services We have the right to suspend the benefit of any Credit Union service at any time for reasonable cause. At Our discretion, We also have the right to pay any share draft presented for payment from Your Account after Your Account is closed or suspended and to recover such amount paid from You.