DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule. 2.4.2 The XXXX will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX to construct the Project. Before initiating construction operations, the XXXX may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents. 2.4.3 The XXXX will meet with the Project Team as required to review designs during their development. The XXXX will familiarize itself with the evolving documents through the various design phases. The XXXX will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX will recommend cost effective alternatives. 2.4.4 The XXXX will routinely conduct constructability and bidability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
Appears in 4 contracts
Samples: Design Phase Services Contract, Design Phase Services, Design Phase Services Contract
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will 9.1. CM@Risk shall periodically evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; design and other factors that may impact the cost estimateCost Model, GMP Proposals and/or the Construction ScheduleProject schedule and update each accordingly.
2.4.2 The XXXX 9.2. CM@Risk will recommendidentify, in conjunction with the Project Team, those any additional surface and subsurface investigations that, in its professional opinion, that are required to provide the necessary information for the XXXX to construct construction of the Project. Before initiating After completion of pre- construction operationsphase services, the XXXX CM@Risk may request provide additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data the Data made available with the Construction Documentsconstruction documents. CM@Risk will be responsible for the time and cost required to obtain such additional investigations, except if otherwise provided by specific additional services.
2.4.3 The XXXX 9.3. CM@Risk will meet with the Project Team as required required, to review designs during their development. The XXXX CM@Risk will thoroughly familiarize itself with the evolving documents through the various conceptual design, preliminary design phasesand development of detailed design documents. The XXXX CM@Risk will proactively advise the Project Team and make recommendations on factors related to construction costs, costs and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, systems and labor and material availability. The XXXX CM@Risk will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, as any concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX CM@Risk will recommend cost effective alternatives.
2.4.4 The XXXX will routinely conduct constructability and bidability reviews of the Construction Documents as 9.4. As necessary to satisfy the needs of the Project Team, CM@Risk will routinely conduct constructability and biddability reviews of the Drawings and Specifications. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents construction documents, especially those related to clarity, consistency, consistency and coordination of Work for Subcontractors and Suppliers.
Appears in 2 contracts
Samples: Contract for Construction Manager at Risk Pre Construction Phase Services, Contract for Construction Manager at Risk Pre Construction Phase Services
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX CMARE will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX CMARE will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX CMARE to construct the Project. Before initiating construction operations, the XXXX CMARE may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX CMARE will meet with the Project Team as required to review designs during their development. The XXXX CMARE will familiarize itself with the evolving documents through the various design phases. The XXXX CMARE will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX CMARE will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, as concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX CMARE will recommend cost effective alternatives.
2.4.4 The XXXX CMARE will routinely conduct constructability and bidability biddability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
2.4.4.1 Constructability Reviews: The CMARE will evaluate whether (a) the Drawings and Specifications are configured to enable efficient construction, (b) design elements are standardized, (c) construction efficiency is properly considered in the Drawings and Specifications, (d) module/preassembly design are prepared to facilitate fabrication, transport and installation, (e) the design promotes accessibility of personnel, material and equipment and facilitates construction under adverse weather conditions, (f) sequences of Work required by or inferable from the Drawings and Specifications are practicable, and
Appears in 2 contracts
Samples: Pre Construction Services Agreement, Pre Construction Services Contract
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX CM will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX CM will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX CM to construct the Project. Before initiating construction operations, the XXXX CM may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX CM will meet with the Project Team as required to review designs during their development. The XXXX CM will familiarize itself with the evolving documents through the various design phases. The XXXX CM will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX CM will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX CM will recommend cost effective alternatives.
2.4.4 The XXXX CM will routinely conduct constructability and bidability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
Appears in 2 contracts
Samples: Design Phase Services Contract, Design Phase Services Agreement
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX to construct the Project. Before initiating construction operations, the XXXX may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX will meet with the Project Team as required to review designs during their development. The XXXX will familiarize itself with the evolving documents through the various design phases. The XXXX will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and DocuSign Envelope ID: 31AC7B5A-B8C9-4688-A97F-D0940E9127AE material availability. The XXXX will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX will recommend cost effective alternatives.
2.4.4 The XXXX will routinely conduct constructability and bidability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
Appears in 1 contract
Samples: Design Phase Services Contract
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX CMARE will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX CMARE will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX CMARE to construct the Project. Before initiating construction operations, the XXXX CMARE may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX CMARE will meet with the Project Team as required to review designs during their development. The XXXX CMARE will familiarize itself with the evolving documents through the various design phases. The XXXX CMARE will proactively advise the Project Team and make recommendations on factors related to construction costs, costs and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, and labor and material availability. The XXXX CMARE will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, considerations including concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX CMARE will recommend cost effective alternatives.
2.4.4 The XXXX CMARE will routinely conduct constructability and bidability biddability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
2.4.4.1 Constructability Reviews: The CMARE will evaluate whether (a) the Drawings and Specifications are configured to enable efficient construction, (b) design elements are standardized, (c) construction efficiency is properly considered in the Drawings and Specifications, (d) module/preassembly design are prepared to facilitate fabrication, transport and installation, (e) the design promotes accessibility of personnel, material and equipment and facilitates construction under adverse weather conditions, (f) sequences of Work required by or inferable from the Drawings and Specifications are practicable, and
Appears in 1 contract
Samples: Pre Construction Services Contract
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX CMARE will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX CMARE will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX CMARE to construct the Project. Before initiating construction operations, the XXXX CMARE may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX CMARE will meet with the Project Team as required to review designs during their development. The XXXX CMARE will familiarize itself with the evolving documents through the various design phases. The XXXX CMARE will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX CMARE will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX CMARE will recommend cost effective alternatives.
2.4.4 The XXXX CMARE will routinely conduct constructability and bidability biddability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
2.4.4.1 Constructability Reviews: The CMARE will evaluate whether (a) the Drawings and Specifications are configured to enable efficient construction, (b) design elements are standardized, (c) construction efficiency is properly considered in the Drawings and Specifications, (d) module/preassembly design are prepared to facilitate fabrication, transport and installation, (e) the design promotes accessibility of personnel, material and equipment and facilitates construction under adverse weather conditions, (f) sequences of Work required by or inferable from the Drawings and Specifications are practicable, and
Appears in 1 contract
Samples: Pre Construction Services Contract
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will 17.4.1 CM@Risk must evaluate periodically the availability of labor, materials/equipment, building systems, cost-cost- sensitive aspects of the design; and other factors that may impact create an unacceptable variance to the cost estimate, GMP Proposals Baseline Cost Model and/or the Construction Baseline Project Schedule.
2.4.2 The XXXX will 17.4.2 CM@Risk must recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX CM@Risk to construct the Project. Before initiating construction operationsThese additional investigations, if agreed to be necessary by the XXXX may request additional investigations in their GMP Proposal to improve Project Manager and the adequacy Design Professional, will be acquired by City and completeness copies of the site condition information and data made available with the Construction Documentsreports will be provided to CM@Risk.
2.4.3 The XXXX will 17.4.3 CM@Risk must meet with the Project Team as required to review designs during their development. The XXXX will CM@Risk must familiarize itself with the evolving documents through the various design phasespre- construction. The XXXX will CM@Risk must proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX will CM@Risk must furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX will recommend CM@Risk must use established value analysis principles in recommending cost effective alternatives.
2.4.4 The XXXX will 17.4.4 CM@Risk must routinely conduct constructability and bidability bid-ability reviews of the Construction Documents Drawings and Specifications as necessary to satisfy the needs of the Project Team. The reviews will must attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, completeness and coordination of Work for of Subcontractors and Suppliers.
17.4.4.1 CM@Risk must evaluate whether: (a) the Drawings and Specifications are configured to enable efficient construction; (b) design elements are standardized; (c) construction efficiency is properly considered in the Drawings and Specifications; (d) module/preassembly design is prepared to facilitate fabrication, transport and installation;
Appears in 1 contract
Samples: Construction Agreement
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will shall evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Project Master Schedule.
2.4.2 The XXXX will shall recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX to construct the Project. Before initiating construction operations, the XXXX may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site Site condition information and data made available with the Construction Documents.
2.4.3 The XXXX will shall meet with the Project Team Team, as required required, to review designs during their development. The XXXX will shall familiarize itself with the evolving documents through the various design phases. The XXXX will shall proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, and labor and material availability. The XXXX will furthermore shall advise the Project Team on proposed site Site improvements, excavation and foundation considerations, as well as, as concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX will shall recommend cost effective alternatives.
2.4.4 The XXXX will routinely shall conduct constructability and bidability reviews of the Construction Documents Drawings and Specifications as necessary to satisfy the needs of the Project TeamTeam and at a minimum as scheduled and identified by milestones in the Project Master Schedule required in Article 2.3 above. The reviews will shall attempt to identify all discrepancies and inconsistencies in the Construction Documents Documents, especially those related to clarity, consistency, and coordination of Work for of Subcontractors and Suppliers.
Appears in 1 contract
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will 17.4.1 CM@Risk must evaluate periodically the availability of labor, materials/equipment, building systems, cost-cost- sensitive aspects of the design; and other factors that may impact create an unacceptable variance to the cost estimate, GMP Proposals Baseline Cost Model and/or the Construction Baseline Project Schedule.
2.4.2 The XXXX will 17.4.2 CM@Risk must recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX CM@Risk to construct the Project. Before initiating construction operationsThese additional investigations, if agreed to be necessary by the XXXX may request additional investigations in their GMP Proposal to improve Project Manager and the adequacy Design Professional, will be acquired by City and completeness copies of the site condition information and data made available with the Construction Documentsreports will be provided to CM@Risk.
2.4.3 The XXXX will 17.4.3 CM@Risk must meet with the Project Team as required to review designs during their development. The XXXX will CM@Risk must familiarize itself with the evolving documents through the various design phasespre- construction. The XXXX will CM@Risk must proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX will CM@Risk must furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX will recommend CM@Risk must use established value analysis principles in recommending cost effective alternatives.alternatives.β
2.4.4 The XXXX will 17.4.4 CM@Risk must routinely conduct constructability and bidability bid-ability reviews of the Construction Documents Drawings and Specifications as necessary to satisfy the needs of the Project Team. The reviews will must attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, completeness and coordination of Work for of Subcontractors and Suppliers.
17.4.4.1 CM@Risk must evaluate whether: (a) the Drawings and Specifications are configured to enable efficient construction; (b) design elements are standardized; (c) construction efficiency is properly considered in the Drawings and Specifications; (d) module/preassembly design is prepared to facilitate fabrication, transport and installation;
Appears in 1 contract
Samples: Construction Agreement
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX to construct the Project. Before initiating construction operations, the XXXX may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX will meet with the Project Team as required to review designs during their development. The XXXX will familiarize itself with the evolving documents through the various design phasesphases of design. The XXXX will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX will recommend and implement cost effective alternatives, as approved by the County.
2.4.4 The XXXX will routinely conduct constructability and bidability biddability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
2.4.4.1 Constructability Reviews: The XXXX will evaluate whether (a) the Drawings and Specifications are configured to enable efficient construction, (b) design elements are standardized, (c) construction efficiency is properly considered in the Drawings and Specifications, (d) module/preassembly design are prepared to facilitate fabrication, transport and installation, (e) the design promotes accessibility of personnel, material and equipment and facilitates construction under adverse weather conditions, (f) sequences of Work required by or inferable from the Drawings and Specifications are practicable, and
Appears in 1 contract
Samples: Design Phases Services
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX to construct the Project. Before initiating construction operations, the XXXX may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX will meet with the Project Team as required to review designs during their development. The XXXX will familiarize itself with the evolving documents through the various design phases. The XXXX will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX will recommend cost effective alternatives.
2.4.4 The XXXX will routinely conduct constructability and bidability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
2.4.4.1 Constructability Reviews: The XXXX will evaluate whether (a) the Drawings and Specifications are configured to enable efficient construction, (b) design elements are standardized, (c) construction efficiency is properly considered in the Drawings and Specifications, (d) module/preassembly design are prepared to facilitate fabrication, transport and installation, (e) the design promotes accessibility of personnel, material and equipment and facilitates construction under adverse weather conditions, (f) sequences of Work required by or inferable from the Drawings and Specifications are practicable, and (g) the design has taken into consideration, efficiency issues concerning; access and entrance to the site, laydown and storage of materials, staging of site facilities, construction parking, and other similar pertinent issues.
Appears in 1 contract
Samples: Design Phase Services Contract
DESIGN DOCUMENT REVIEWS. 2.4.1 The XXXX CMARE will evaluate periodically the availability of labor, materials/equipment, building systems, cost-sensitive aspects of the design; and other factors that may impact the cost estimate, GMP Proposals and/or the Construction Schedule.
2.4.2 The XXXX CMARE will recommend, in conjunction with the Project Team, those additional surface and subsurface investigations that, in its professional opinion, are required to provide the necessary information for the XXXX CMARE to construct the Project. Before initiating construction operations, the XXXX CMARE may request additional investigations in their GMP Proposal to improve the adequacy and completeness of the site condition information and data made available with the Construction Documents.
2.4.3 The XXXX CMARE will meet with the Project Team as required to review designs during their development. The XXXX CMARE will familiarize itself with the evolving documents through the various design phases. The XXXX CMARE will proactively advise the Project Team and make recommendations on factors related to construction costs, and concerns pertaining to the feasibility and practicality of any proposed means and methods, selected materials, equipment and building systems, and, labor and material availability. The XXXX CMARE will furthermore advise the Project Team on proposed site improvements, excavation and foundation considerations, as well as, concerns that exist with respect to coordination of the Drawings and Specifications. The XXXX CMARE will recommend cost effective alternatives.
2.4.4 The XXXX CMARE will routinely conduct constructability and bidability reviews of the Construction Documents as necessary to satisfy the needs of the Project Team. The reviews will attempt to identify all discrepancies and inconsistencies in the Construction Documents especially those related to clarity, consistency, and coordination of Work for Subcontractors and Suppliers.
2.4.4.1 Constructability Reviews: The CMARE will evaluate whether (a) the Drawings and Specifications are configured to enable efficient construction, (b) design elements are standardized, (c) construction efficiency is properly considered in the Drawings and Specifications, (d) module/preassembly design are prepared to facilitate fabrication, transport and installation, (e) the design promotes accessibility of personnel, material and equipment and facilitates construction under adverse weather conditions, (f) sequences of Work required by or inferable from the Drawings and Specifications are practicable, and (g) the design has taken into consideration, efficiency issues concerning; access and entrance to the site, laydown and storage of materials, staging of site facilities, construction parking, and other similar pertinent issues. The CMARE shall identify, to the greatest extent practicable, discrepancies and inconsistencies in the Construction Documents.
Appears in 1 contract
Samples: Design Phase Services