Design Schedule. The project design schedule, excluding approval time, is approximately five (5) months with the following times for each design phase: A. Preliminary Report: 60 Days B. Final Plans and Specifications: 90 Days The construction sequencing must not interfere with ongoing instructional operations.
Appears in 3 contracts
Samples: Contract for Architectural Services, Contract for Architectural Services, Contract for Architectural Services
Design Schedule. The total project design schedule, excluding approval time, is approximately five seven (57) months with the following times for each design phase:
A. Site Selection 45 Days B. Schematic Design: 30 Days C. Preliminary Report: 60 Days
B. Days D. Final Plans and Specifications: 90 Days The construction sequencing must not interfere with ongoing instructional operations.Days
Appears in 1 contract
Samples: Construction Contract
Design Schedule. The total project design schedule, excluding approval time, is approximately five six (56) months with the following times for each design phase:
A. a) Schematic Design: 45 Days
b) Preliminary Report: 60 45 Days
B. c) Final Plans and Specifications: 90 75 Days The construction sequencing must not interfere with ongoing instructional operations.
Appears in 1 contract
Samples: Contract for Architectural Services
Design Schedule. The total project design schedule, excluding approval time, is approximately five (5) months with the following times for each design phase:
A. a) Schematic Design: 30 Days
b) Preliminary Report: 60 Days
B. c) Final Plans and Specifications: 90 60 Days The construction sequencing must not interfere with ongoing instructional operations.
Appears in 1 contract
Samples: Contract for Architectural Services