Dispatch Coordination. During the startup, testing and commissioning of the Plant, Seller shall coordinate with Buyer’s Representative and Buyer’s operating personnel the orderly startup and shut-down of the Plant. Ninety (90) days prior to the initial startup of the Plant, Seller shall provide to Buyer a schedule of dispatch for the Plant during the commissioning period, including expected net plant output, duration of the commissioning activity and expected fuel usage. Within thirty (30) days of the initial startup of the Plant, Seller shall provide to Buyer an update to this schedule and thereafter on a weekly basis until Substantial Completion is achieved. Seller shall also provide 72 hours’ advance notice to Buyer of the planned Pant dispatch profile including net plant output, duration of the commissioning period and expected fuel usage.
Appears in 3 contracts
Samples: Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement
Dispatch Coordination. During the startup, testing and commissioning of the Plant, Seller shall coordinate with Buyer’s Representative and Buyer’s operating personnel the orderly startup and shut-down of the Plant. Ninety (90) days prior to the initial startup of the Plant, Seller shall provide to Buyer a schedule of dispatch for the Plant during the commissioning period, including expected net plant output, duration of the commissioning activity and expected fuel usage. Within thirty (30) days of the initial startup of the Plant, Seller shall provide to Buyer an update to this schedule and thereafter on a weekly basis until Substantial Completion is achieved. Seller shall also provide 72 hours’ advance notice to Buyer of the planned Pant dispatch profile including net plant output, duration of the commissioning period and expected fuel usage.
Appears in 3 contracts
Samples: Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement
Dispatch Coordination. During the startup, testing and commissioning of the Plant, Seller shall coordinate with BuyerXxxxx’s Representative and BuyerXxxxx’s operating personnel the orderly startup and shut-down of the Plant. Ninety (90) days prior to the initial startup of the Plant, Seller shall provide to Buyer a schedule of dispatch for the Plant during the commissioning period, including expected net plant output, duration of the commissioning activity and expected fuel usage. Within thirty (30) days of the initial startup of the Plant, Seller shall provide to Buyer an update to this schedule and thereafter on a weekly basis until Substantial Completion is achieved. Seller shall also provide 72 hours’ advance notice to Buyer of the planned Pant dispatch profile including net plant output, duration of the commissioning period and expected fuel usage.
Appears in 3 contracts
Samples: Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement
Dispatch Coordination. During the startup, testing and commissioning of the Plant, Seller shall coordinate with BuyerXxxxx’s Representative and BuyerXxxxx’s operating personnel the orderly startup and shut-down of the Plant. Ninety (90) days prior to the initial startup of the Plant, Seller shall provide to Buyer a schedule of dispatch for the Plant during the commissioning period, including expected net plant output, duration of the commissioning activity and expected fuel usage. Within thirty (30) days of the initial startup of the Plant, Seller shall provide to Buyer an update to this schedule and thereafter on a weekly basis until Substantial Completion is achieved. Seller shall also provide 72 hours’ advance notice to Buyer of the planned Pant dispatch profile including net plant output, duration of the commissioning period and expected fuel usage.
Appears in 2 contracts
Samples: Asset Purchase and Sale Agreement, Asset Purchase and Sale Agreement