Duration of the public contract Sample Clauses

Duration of the public contract. The contract starts upon award notification and expires upon final acceptance. No renewal of the contract is provided for.
AutoNDA by SimpleDocs
Duration of the public contract. The contract starts upon award notification and lasts for 45 calendar days. Thereafter, the defects liability period of 06 calendar months shall commence from the day following date of provisional acceptance
Duration of the public contract. The duration of the contract will be 701 calendar days. For each of the lots, the works shall be completed within 336 calendar days from the date of award of contract. The Defects Liability Period (DLP) will commence thereafter and end within 365 calendar days.
Duration of the public contract. The contract starts with the awarding letter and ends by final acceptance.
Duration of the public contract. For each of the lots, the contract starts upon award notification and lasts until 31 December 2026. This duration of the contract shall not to be confused with period of performance (see “4.11 Performance modalities (Art. 146 et seq.).32”.
Duration of the public contract. The procurement contract starts upon award notification and lasts 4 calendar years . Implementation period of each service order shall start upon receipt of each order and lasts: 195 calender days for a service order on 3 institutions, 130 calendar days for a service order on 2 institutions and 65 calendar days for a service order on 1 institution.
Duration of the public contract. For each of the lots, the contract starts upon award notification and expires at the final
AutoNDA by SimpleDocs
Duration of the public contract. For each lot, the contract starts the day after receipt of award notification letter and last up to final acceptance date.
Duration of the public contract. For each of the lots, the contract shall commence upon award notification and last for a duration of 4 calendar years Each party may, however, terminate the agreement at the end of the first, second or third year, provided that notification to the other party is sent at least 90 calendar days before the end of the first, second or third year of the framework agreement. In this case, the party may not claim damages for such termination. If the framework agreement is terminated by the contracting authority, such termination will apply to all participants and, consequently, it will be notified to all participants. Participants may not claim damages for such termination. Where the framework agreement is terminated in application of an ex officio measure, termination of the agreement is limited to the participant against whom the ex-officio measure was taken. If the termination of the framework agreement is initiated by one of the participants, they will be deleted as a participant from the second, third or fourth year of the framework agreement, as the case may be. As soon as they are removed as a participant, they will no longer be considered for contracts based on the framework agreement. Within three years of the conclusion of this contract and in accordance with Article 42 §1, 2° of the law of 17 June 2016, the contract may be extended to include new services consisting of the repetition of similar works or services.
Duration of the public contract. For each of the lots, the contract starts on the first calendar day following the day the awardee receives notification of the contract's conclusion and lasts until the last day of the legal warranty period for the goods. The duration of the public procurement contract should not be confused with the performance period or the delivery schedule. The performance period is outlined in Point 4.11.1 Deadlines and terms (Art. 116), p.31.