Failure to Achieve Guranteed Commerical Operation Date Sample Clauses

Failure to Achieve Guranteed Commerical Operation Date. (a) PGE’s exclusive remedies for the Facility’s failure to achieve Commercial Operation by the Scheduled Commercial Operation Date or by the Guaranteed Commercial Operation Date, as applicable, shall be (i) the payment by Seller of Delay Damages and, if applicable, Contract Termination Damages, as provided in Section 3.1.16 and Section 3.1.17, (ii) the right of first offer set forth in Section 3.1.19, and/or (iii) the exercise of step in rights under Section 9.5. (b) PGE’s exclusive remedies for the Facility’s failure to achieve Commercial Operation of the full Generating Facility Nameplate Capacity of 120MWAC on or before the Capacity Shortfall Date, if applicable, shall be the payment by Seller of Capacity Shortfall Damages and, if applicable, the Capacity Shortfall Payment, each as provided in Section 3.1.21(c).
AutoNDA by SimpleDocs

Related to Failure to Achieve Guranteed Commerical Operation Date

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Commercial Milestones (a) Within [*****] calendar days after the end of the first Calendar Year in which aggregate annual Net Sales for that Calendar Year for the Licensed Product in the Territory reach any threshold indicated in the Commercial Milestone Events listed below, EverInsight shall notify VistaGen of the achievement of such Commercial Milestone Event and VistaGen shall invoice EverInsight for the corresponding non-refundable, non-creditable Milestone Payment set forth below and EverInsight shall remit payment to VistaGen within [*****] Business Days after the receipt of the invoice, as described in Section 8.6 (Currency; Exchange Rate; Payments). Annual Net Sales Milestones for Licensed Product Milestone Payments (in Dollars) (each a “Commercial Milestone Event”): (1). [*****] (2). [*****] (3). [*****] (4). [*****] (5). [*****] (b) For the purposes of determining whether a Net Sales Milestone Event has been achieved, Net Sales of Licensed Product(s) in the Territory shall be aggregated. For clarity, the annual Net Sales Milestone Payments set forth in this Section 8.3 (Commercial Milestones) shall be payable only once, upon the first achievement of the applicable Commercial Milestone Event, regardless of how many times such Commercial Milestone Event is achieved. (c) If a Commercial Milestone Event in Section 8.3 (Commercial Milestones) is achieved and payment with respect to any previous Commercial Milestone Event in Section 8.3 has not been made, then such previous Commercial Milestone Event shall be deemed achieved and EverInsight shall notify VistaGen within fifteen (15) calendar days of such achievement. VistaGen shall then invoice EverInsight for such unpaid previous Commercial Milestone Event(s) and EverInsight shall pay VistaGen such unpaid previous milestone payment(s) within thirty (30) Business Days of receipt of such invoice. (d) In the event that, VistaGen believes any Commercial Milestone Event under Section 8.3(a) has occurred but EverInsight has not given VistaGen the notice of the achievement of such Commercial Milestone Event, it shall so notify EverInsight in writing and shall provide to EverInsight data, documentation or other information that supports its belief. Any dispute under this Section 8.3(d) (Commercial Milestones - subsection (d)) that relates to whether or not a Commercial Milestone Event has occurred shall be referred to the JSC to be resolved in accordance with ARTICLE 3 (Governance) and shall be subject to resolution in accordance with Section 14.10 (Dispute Resolution). The Milestone Payments made for each Commercial Milestone Event shall be non-creditable and non-refundable.

  • No Release; Return or Destruction Each Party agrees not to release or disclose, or permit to be released or disclosed, any information addressed in Section 6.9(a) to any other Person, except its Representatives who need to know such information in their capacities as such (who shall be advised of their obligations hereunder with respect to such information), and except in compliance with Section 6.10. Without limiting the foregoing, when any such information is no longer needed for the purposes contemplated by this Agreement or any Ancillary Agreement, and is no longer subject to any legal hold or other document preservation obligation, each Party will promptly after request of the other Party either return to the other Party all such information in a tangible form (including all copies thereof and all notes, extracts or summaries based thereon) or notify the other Party in writing that it has destroyed such information (and such copies thereof and such notes, extracts or summaries based thereon); provided, that the Parties may retain electronic back-up versions of such information maintained on routine computer system backup tapes, disks or other backup storage devices; provided further, that any such information so retained shall remain subject to the confidentiality provisions of this Agreement or any Ancillary Agreement.

  • Service Level In the event that League InfoSight discovers or is notified by you of the existence of Non-Scheduled Downtime, we will use commercially reasonable efforts to determine the source of the problem and attempt to resolve it as quickly as possible.

  • Staffing Levels To the extent legislative appropriations and PIN authorizations allow, safe staffing levels will be maintained in all institutions where employees have patient, client, inmate or student care responsibilities. In July of each year, the Secretary or Deputy Secretary of each agency will, upon request, meet with the Union, to hear the employees’ views regarding staffing levels. In August of each year, the Secretary or Deputy Secretary of Budget and Management will, upon request, meet with the Union to hear the employees’ views regarding the Governor’s budget request.

  • CLEC OUTAGE For a problem limited to one CLEC (or a building with multiple CLECs), BellSouth has several options available for restoring service quickly. For those CLECs that have agreements with other CLECs, BellSouth can immediately start directing traffic to a provisional CLEC for completion. This alternative is dependent upon BellSouth having concurrence from the affected CLECs. Whether or not the affected CLECs have requested a traffic transfer to another CLEC will not impact BellSouth's resolve to re-establish traffic to the original destination as quickly as possible.

  • Excuse for Nonperformance or Delayed Performance Except with respect to defaults of subcontractors, Contractor/Vendor shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure by Contractor/Vendor to make progress in the prosecution of the work hereunder which endangers such performance) if Contractor/Vendor has notified the Commission or designee within 15 days after the cause of the delay and the failure arises out of causes such as: acts of God; acts of the public enemy; acts of the State and any other governmental entity in its sovereign or contractual capacity; fires; floods; epidemics; quarantine restrictions; strikes or other labor disputes; freight embargoes; or unusually severe weather. If the failure to perform is caused by the failure of a subcontractor to perform or to make progress, and if such failure arises out of causes similar to those set forth above, Contractor/Vendor shall not be deemed to be in default, unless the services to be furnished by the subcontractor were reasonably obtainable from other sources in sufficient time to permit Contractor to meet the contract requirements. Upon request of Contractor, the Commission or designee shall ascertain the facts and extent of such failure, and, if such officer determines that any failure to perform was occasioned by any one or more of the excusable causes, and that, but for the excusable cause, Contractor’s progress and performance would have met the terms of the contract, the delivery schedule shall be revised accordingly, subject to the rights of the State under the clause entitled (in fixed-price contracts, “Termination for Convenience,” in cost-reimbursement contracts, “Termination”). (As used in this Paragraph of this clause, the term “subcontractor” means subcontractor at any tier).

  • Performance Delay Time is of the essence in the Vendor’s performance of this Agreement. If at any time it appears to Vendor that it may not meet any of the performance schedules or the scheduled completion date of the services to be performed for any reason, including labor disputes, Vendor shall immediately by verbal means (to be confirmed in writing) notify Customer of the reasons for and the estimated duration of such delay. If requested by Customer, Vendor shall make every effort to avoid or minimize the delay to the maximum extent possible including the expenditure of premium time. Any additional cost caused by these requirements of Customer shall be borne by Vendor, unless the delay in performance arises out of causes beyond the control and without the fault or negligence of Vendor or its subcontractors within the meaning of the Cancellation- Default clause herein. The foregoing requirements are in addition to any of Customer’s other rights and remedies as may be provided by law or this Agreement.

  • Measurement Period In this Agreement, unless the contrary intention appears, a reference to: