Common use of Fossils Clause in Contracts

Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract Awarder. The Contractor shall take reasonable precautions to prevent Contractor's Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract Awarder, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to:

Appears in 2 contracts

Samples: Contract Agreement (Renewable Fuel Corp), Contract Agreement (Renewable Fuel Corp)

AutoNDA by SimpleDocs

Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract AwarderEmployer. The Contractor shall take reasonable precautions to prevent Contractor's Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract AwarderEngineer, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's Contractors Claims] to:

Appears in 2 contracts

Samples: Contract Agreement, Contract Agreement

Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract AwarderEmployer. The Contractor shall take reasonable precautions to prevent Contractor's Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract AwarderEngineer, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's ’s Claims] to:

Appears in 1 contract

Samples: Contract Agreement

AutoNDA by SimpleDocs

Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract AwarderEmployer. The Contractor shall take reasonable precautions to prevent Contractor's ’s Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract AwarderEngineer, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's ’s Claims] to:

Appears in 1 contract

Samples: Contract Agreement Unit Price Contract

Time is Money Join Law Insider Premium to draft better contracts faster.