Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract Awarder. The Contractor shall take reasonable precautions to prevent Contractor's Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract Awarder, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder and shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to: (a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and (b) payment of any such Cost, which shall be added to the Contract Price. After receiving this further notice, the Contract Awarder shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.
Appears in 2 contracts
Samples: Contract Agreement (Renewable Fuel Corp), Contract Agreement (Renewable Fuel Corp)
Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract AwarderEmployer. The Contractor shall take reasonable precautions to prevent Contractor's Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract AwarderEngineer, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's Contractors Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost, which shall be added to included in the Contract Price. After receiving this further notice, the Contract Awarder Engineer shall proceed in accordance with Sub-Sub- Clause 3.5 [Determinations] to agree or determine these matters.
Appears in 2 contracts
Samples: Contract Agreement, Contract Agreement
Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract AwarderEmployer. The Contractor shall take reasonable precautions to prevent Contractor's Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract AwarderEngineer, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's ’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost, which shall be added to included in the Contract Price. After receiving this further notice, the Contract Awarder shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.
Appears in 1 contract
Samples: Contract Agreement
Fossils. All fossils, coins, articles of value or antiquity, and structures and other remains or items of geological or archaeological interest found on the Work Site shall be placed under the care and authority of the Contract AwarderEmployer. The Contractor shall take reasonable precautions to prevent Contractor's ’s Personnel or other persons from removing or damaging any of these findings. The Contractor shall, upon discovery of any such finding, promptly give notice to the Contract AwarderEngineer, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Contract Awarder Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor's ’s Claims] to:
(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost, which shall be added to included in the Contract Price. After receiving this further notice, the Contract Awarder Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.
Appears in 1 contract
Samples: Unit Price Contract