General Conditions Costs. Construction Manager is entitled to receive payment for the actual cost of the allowable General Conditions items incurred after receipt of a Notice to Proceed with Construction from the Owner through Substantial Completion of the Project plus thirty (30) calendar days. Construction Manager is not entitled to reimbursement for General Conditions Costs incurred before receipt of the Notice to Proceed. General Conditions Costs incurred after Substantial Completion must be approved in advance by the Owner. Allowable General Conditions items are identified below and by attached exhibit. These items shall be included in the General Conditions cost amount shown as a line item in the Guaranteed Maximum Price Proposal and as detailed on the schedule of values. Items not specifically included below or in the exhibit will not be allowed as a General Condition costs.
Appears in 25 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement, Construction Manager at Risk Agreement
General Conditions Costs. Construction Manager is entitled to receive payment for the actual cost of the allowable General Conditions items Costs incurred after receipt of a Notice to Proceed with Construction from the Owner through Substantial Completion of the Project plus thirty (30) calendar days. Construction Manager is not entitled to reimbursement for General Conditions Costs incurred before receipt of the Notice to Proceed. General Conditions Costs incurred after Substantial Completion must be approved in advance by the Owner. Allowable Items that are allowable as General Conditions items Costs are identified below and by attached exhibit. These items shall be included in the General Conditions cost amount Costs shown as a line item in the Guaranteed Maximum Price Proposal and as detailed on the schedule Schedule of valuesValues. Items not specifically included below or in the exhibit will not be allowed as a General Condition costsConditions Costs.
Appears in 6 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
General Conditions Costs. Construction Manager is entitled to receive payment for the actual cost of the allowable General Conditions items Costs incurred after receipt of a Notice to Proceed with Construction from the Owner through Substantial Completion of the Project plus thirty (30) calendar days. Construction Manager is not entitled to reimbursement for General Conditions Costs incurred before receipt of the Notice to Proceed. General Conditions Costs incurred after Substantial Completion must be approved in advance by the Owner. Allowable Items that are allowable as General Conditions items Costs are identified below and by attached exhibit. These items shall be included in the General Conditions cost amount Costs shown as a line item in the Guaranteed Maximum Price Proposal and as detailed on the schedule Schedule of valuesValues. Items not specifically included below or in the exhibit will not be allowed as a General Condition costsConditions Costs.
Appears in 2 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement
General Conditions Costs. Construction Manager is entitled to receive payment for the actual cost of the allowable General Conditions items incurred after receipt of a Notice to Proceed with Construction from the Owner through Substantial Completion of the Project plus thirty (30) calendar daysProject. Construction Manager is not entitled to reimbursement for General Conditions Costs incurred before receipt of the Notice to Proceed. General Conditions Costs incurred after Substantial Completion must be approved in advance by the Owner. Allowable General Conditions items are identified below and by attached exhibit. These items shall be included in the General Conditions cost amount shown as a line item in the Guaranteed Maximum Price Proposal and as detailed on the schedule of values. Items not specifically included below or in the exhibit will not be allowed as a General Condition costs.
Appears in 1 contract
Samples: Construction Manager Agreement
General Conditions Costs. Construction Manager is entitled to receive payment for the actual cost of the allowable General Conditions items incurred after receipt of a Notice to Proceed with Construction from the Owner through Substantial Completion of the Project plus thirty (30) calendar daysProject. Construction Manager is not entitled to reimbursement for General Conditions Costs incurred before receipt of the Notice to ProceedProceed with Construction. General Conditions Costs incurred after Substantial Completion must be approved in advance by the Owner. Allowable General Conditions items are identified below and by attached exhibit. These items shall be included in the General Conditions cost amount shown as a line item in the Guaranteed Maximum Price Proposal and as detailed on the schedule of values. Items not specifically included below or in the exhibit will not be allowed as a General Condition costs.
Appears in 1 contract
Samples: Construction Manager Agreement