Hoisting & Rigging. 3.1 Client shall coordinate the delivery of any Client-procured equipment and materials to the site (or to alternate location if requested by EPC Contractor). Commercially reasonable efforts will be made to adhere to the Purchasers requested delivery schedule. 3.2 In the event that any EPC Contractor-procured equipment and materials are found to be damaged or defective (“Defective Materials”), EPC Contractor shall be solely responsible for the replacement thereof, including but not limited to costs related to: (a) removal of Defective Materials from the Site, (b) procurement of replacement equipment and materials (“Replacement Materials”) for the Defective Materials, and (c) delivery of the Replacement Materials to the point of installation on the Site. Without limiting the generality of the foregoing, in the event any special equipment or additional labor is required to deliver the Replacement Materials to the point of installation, EPC Contractor shall be responsible for payment of all additional costs relating to such special equipment and additional labor. 3.3 Conform to the guidelines on the structural drawings for roof loading restrictions when hoisting and staging equipment on the roof. EPC Contractor shall provide rules and guidelines to Client prior to construction start. EPC Contractor shall use resources provided to create a well-defined proposed staging plan. Client will review staging plan and provide feedback or approve. An Client-approved staging plan is required two (2) weeks prior to the start of hoisting.
Appears in 3 contracts
Samples: Epc Agreement, Epc Agreement, Epc Agreement
Hoisting & Rigging. 3.1 Client shall coordinate the delivery of any Client-procured equipment and materials to the site (or to alternate location if requested by EPC Contractor). Commercially reasonable efforts will be made to adhere to the Purchasers Project Site Owner’s requested delivery schedule.
3.2 In the event that any EPC Contractor-procured equipment and materials are found to be damaged or defective (“Defective Materials”), EPC Contractor shall be solely responsible for the replacement thereof, including but not limited to costs related to: (a) removal of Defective Materials from the Project Site, (b) procurement of replacement equipment and materials (“Replacement Materials”) for the Defective Materials, and (c) delivery of the Replacement Materials to the point of installation on the Project Site. Without limiting the generality of the foregoing, in the event any special equipment or additional labor is required to deliver the Replacement Materials to the point of installation, EPC Contractor shall be responsible for payment of all additional costs relating to such special equipment and additional labor.
3.3 Conform to the guidelines on the structural drawings for roof loading restrictions when hoisting and staging equipment on the roof. EPC Contractor shall provide rules and guidelines to Client prior to construction start. EPC Contractor shall use resources provided to create a well-defined proposed staging plan. Client will review staging plan and provide feedback or approve. An Client-Client- approved staging plan is required two (2) weeks prior to the start of hoisting.
Appears in 1 contract
Samples: Engineering, Procurement and Construction Agreement