Impact of Construction Delays. In the event that the issuance of a certificate of substantial completion for a facility listed on Exhibit D is delayed by a period of 6 months or longer from the last day of the quarter indicated on Exhibit D for that facility, the HOF Entities will provide prompt written notice to Constellation of such delay, and the Sponsorship Fees will be reduced, to the extent applicable, as set forth in Exhibit H. Any construction delay shall not impact the HOF Entities’ contractual commitment or timelines as it relates to the obligations set forth in this Agreement related to EME financing. Any commodity supply agreements with the HOF Entities related to the delayed facility shall be extended in term by the number of months of the certificate of substantial completion delay at then current market pricing, except to the extent that an existing agreement is in place with respect to such delayed facility or supply quantity purchased.