Liquidated Damages for Delay in achieving COD of Project Sample Clauses

Liquidated Damages for Delay in achieving COD of Project. 6.4.1 If the TSP fails to achieve COD of any Element of the Project or the Project, by the Element’s / Project’s Scheduled COD or such Scheduled COD as extended under Articles 4.4.1 and 4.4.3, then the TSP shall pay to the Nodal Agency, a sum equivalent to 3.33% of Monthly Transmission Charges applicable for the Element of the Project [in case where no Elements have been defined, to be on the Project as a whole] / Project, for each day of delay up to sixty (60) days of delay and beyond that time limit, at the rate of five percent (5%) of the Monthly Transmission Charges applicable to such Element / Project, as liquidated damages for such delay and not as penalty, without prejudice to any rights of the Nodal Agency under the Agreement.
AutoNDA by SimpleDocs
Liquidated Damages for Delay in achieving COD of Project. 6.4.1 If the TSP fails to achieve COD of any Element of the Project or the Project, by the Element’s / Project’s Scheduled COD as extended under Articles 4.4.1 and 4.4.2, then the TSP shall pay to the Long Term Transmission Customer(s), as communicated by the Lead Long Term Transmission Customer, in proportion to their Allocated Project Capacity as on the date seven (7) days prior to the Bid Deadline, a sum equivalent to 3.33% of Monthly Transmission Charges applicable for the Element of the Project [in case where no Elements have been defined, to be on the Project as a whole] / Project, for each day of delay up to sixty (60) days of delay and beyond that time limit, at the rate of five percent (5%) of the Monthly Transmission Charges applicable to such Element / Project, as liquidated damages for such delay and not as penalty, without prejudice to Long Term Transmission Customers’ any rights under the Agreement.
Liquidated Damages for Delay in achieving COD of Project. 6.4.1 If the TSP fails to achieve COD of any Element of the Project or the Project, by the Element’s / Project’s Scheduled COD as extended under Articles 4.4.1 and 4.4.2, then the TSP shall pay to the Long Term Transmission Customer(s), as communicated by the Lead Long Term Transmission Customer, in proportion to their Allocated Project Capacity as on the date seven (7) days prior to the Bid Deadline, a sum equivalent to 3.33% of Monthly Transmission Charges applicable for the Element of the Project [in case where no Elements have been defined, to be on the Project as a whole] / Project, for each day of delay up to sixty (60) days of delay and beyond that time limit, at the rate of five percent (5%) of the Monthly Transmission Charges applicable to such Element / Project, as liquidated damages for such delay and not as penalty, without prejudice to Long Term Transmission Customers’ any rights under the Agreement. Assam Power Distribution Company Limited Meghalaya Energy Corporation Limited Tripura State Electricity Corporation Limited Department of Power, Arunachal Pradesh Manipur State Power Distribution Company Limited Department of Power, Nagaland Power & Electricity Department, Mizoram HVDC BNC, Powergrid SPV [Which is under Incorporation]

Related to Liquidated Damages for Delay in achieving COD of Project

  • No Damages for Delays Notwithstanding any other provision of this contract, Engineer shall not be entitled to claim or receive any compensation as a result of or arising out of any delay, hindrance, disruption, force majeure, impact or interference, foreseen or unforeseen.

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Withholding for unpaid wages and liquidated damages The FHWA or the contacting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (2.) of this section.

  • Liquidated Damages The Company’s obligations to pay any partial liquidated damages or other amounts owing under the Transaction Documents is a continuing obligation of the Company and shall not terminate until all unpaid partial liquidated damages and other amounts have been paid notwithstanding the fact that the instrument or security pursuant to which such partial liquidated damages or other amounts are due and payable shall have been canceled.