MANNER AND TIME OF COMPLETION Sample Clauses

MANNER AND TIME OF COMPLETION. 6.1 The Developer/Promoter is expected to complete the said Unit within 31st July, 2022, as a residential accommodation and the said Residential Complex shall be completed in the usual and normal manner including obtaining completion certificate from the appropriate authority or authorities as the case may be. A certificate issued by the Architect of the said unit in respect of measurement of Net area and quality of construction thereof shall be final conclusive and binding on the Purchasers, provided however it is made clear that in case of variations of measurement of areas of the said unit, the purchase price of the said unit shall be increased or decreased as the case may be.
AutoNDA by SimpleDocs
MANNER AND TIME OF COMPLETION. 5.1 The Owners/Developers will complete the said Unit as a residential accommodation in the usual and normal manner within 36 (thirty six) months from the date hereof subject to force measure as per the specifications mentioned under the SEVENTH SCHEDULE hereunder written. The certificate of the Architect will be final.
MANNER AND TIME OF COMPLETION. 6.1 The Developer/Promoter is expected to complete the said Unit within 31st July, 2022, with grace period of 6 (six) months as a residential accommodation and the said Residential Complex shall be completed in the usual and normal manner including obtaining completion certificate from the appropriate authority or authorities as the case may be. A certificate issued by the Architect of the said unit in respect of measurement of Carpet area and quality of construction thereof shall be final conclusive and binding on the Purchaser, provided however it is made clear that in case of variations of measurement of areas of the said unit, the purchase price of the said unit shall be increased or decreased as the case may be.
MANNER AND TIME OF COMPLETION. 6.1 The Developer is expected to complete the said Unit within with grace period of 6 (six) months as a residential building in the usual and normal manner including obtaining completion certificate from the Kolkata Municipal Corporation or any other authority or authorities as the case may be. A certificate issued by the Architect of the said unit in respect of measurement of Carpet area and Built-up area and quality of construction thereof shall be final conclusive and binding on the Purchaser, provided however it is made clear that in case of variations of measurement of areas of the said unit, the purchase price of the said unit shall be increased or decreased as the case may be.
MANNER AND TIME OF COMPLETION. 36.1 The Vendors/Promoter is expected to complete the said Apartment/Unit within 18th September, 2028 with grace period of 6 (six) months as a residential project including obtaining completion certificate from The Kolkata Municipal Corporation or any other authority or authorities as the case may be. A certificate issued by the Architect of the said Apartment/unit in respect of measurement of Carpet area and Built-up area and quality of construction thereof shall be final conclusive and binding on the Purchaser/Allottee.
MANNER AND TIME OF COMPLETION. 5.1 The Vendor is expected to complete the said Unit within with grace period of 6 (six) months. A certificate issued by the Architect of the said unit in respect of measurement of Carpet area and Super Built-up area and quality of construction thereof shall be final conclusive and binding on the Purchaser, provided however it is made clear that in case of variations of measurement of areas of the said unit, the purchase price of the said unit shall be increased or decreased as the case may be.
MANNER AND TIME OF COMPLETION. 5.1 The Developer shall Endeavour to complete the said Flat for a Residential accommodation by 30th June, 2019 in the usual and normal manner subject to force majeure as specified under the Clause 10 hereto.
AutoNDA by SimpleDocs

Related to MANNER AND TIME OF COMPLETION

  • TIME OF COMPLETION The Owner shall issue a Notice to Proceed identifying the date for commencement of the Work. The commencement date shall be 10 or more days after the date the notice is issued. The Contractor shall achieve substantial completion of the Work within _____________________ (____) calendar days after the commencement date, as such completion date may be extended by approved Change Orders. The time set forth for completion of the Work is an essential element of the Contract.

  • DATE OF COMPLETION The Developer must ensure that the Developer’s Works reach Completion on or before the date or milestone referred to in clause 1 of Schedule 3 of this document.

  • TIME OF COMMENCEMENT AND COMPLETION 2.1 The Contractor shall commence the Work upon the date established in the Notice to Proceed.

  • TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to run.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ « » ] The date of this Agreement. [ « » ] A date set forth in a notice to proceed issued by the Owner. [ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) « » If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

  • Notice of Completion The Interconnection Customer shall notify the Transmission Provider and the Interconnected Transmission Owner in writing when it has completed construction of (i) the Customer Facility;

  • Certification of Completion Certification of completion of the program will be contingent upon Resident successfully completing the core requirements of the Program, returning all property of the Medical Center such as books, equipment, etc., and having settled any other professional or financial obligations to the Medical Center. The certificate will be issued in accordance with the provisions of the ASHP Regulations on Accreditation of Pharmacy Residencies and signed by the RPD and the Chief Executive Officer of the organization. A certificate will not be issued to anyone who does not complete the program’s requirements. Core requirements to successfully complete the program include: • Possess a valid pharmacist license from the Pennsylvania State Board of Pharmacy by October 31st of the residency year. • Successful completion of core learning experiences and required longitudinal learning experiences as defined in the learning experience descriptions • Completion of all R1 goals/objectives with a status of achieved by the end of the residency. Completion of 100% of the remaining goals/objectives for the program with at least 50% of the objectives having a status as achieved. All objectives must have a minimum status of satisfactory progress. • All evaluations must be completed in accordance with ASHP Accreditation Standard as outlined in the Resident Agreement • Completion of pharmacokinetic certification by October 31 of residency year • Completion of inpatient anticoagulation certification by October 31 of residency year. • Completion of major project, which includes meeting all project deadlines and submission of written manuscript of completed project to the RAC. • Assigned projects (MUE, drug review, class review, and management project) have been completed • Presentation of at least one major CME program. • Completion of minimum staffing requirements as described in section 2.7 • Adherence to the organization’s attendance standards and as described in this document under Exhibit A.

  • Commencement and Completion 3.1 The Owner agrees to commence the Restoration Works, Landscaping Works, and Servicing Works forthwith upon adoption of City of Kelowna Heritage Revitalization Agreement Authorization Bylaw No. and to complete the Works no later than August 1, 2006.

  • Time for Completion The Contractor shall deliver the material and/or services called for in the specifications/proposal and within the delivery time specified and in accordance with the terms of the contract. Work shall be completed within 30 days from the Notice to Proceed issued by the City of Sparks Purchasing Division. The Contractor shall not alter or vary any terms or conditions contained or incorporated herein, including but not limited to, the quantity, price, delivery date or date designated as After Receipt of Order (ARO) or date for commencement or completion of services as mutually agreed upon, unless such alteration or variation is consented to in writing by a duly authorized representative of the City. The City reserves the right to cancel resultant Contract upon ten days written notice in the event the type and quality of the product or work performance is unsatisfactory or in default, subject to Contractor’s right to cure as outlined in termination clause. This is a non-exclusive Contract and the City reserves the right to acquire the material and/or services at its discretion, from other sources during the term of this Contract.