Common use of Meeting with the Project Manager Clause in Contracts

Meeting with the Project Manager. 5.4.1 Within 30 days after receipt of the request filed with the Contracting Authority pursuant to Section 5.1, or other period mutually agreed by the parties, the Project Manager shall schedule a meeting to resolve the request and render a decision on the request promptly thereafter or render a decision on the request without a meeting.

Appears in 12 contracts

Samples: dam.assets.ohio.gov, www.utoledo.edu, www-s3-live.kent.edu

AutoNDA by SimpleDocs

Meeting with the Project Manager. 5.4.1 5.5.1 Within 30 days after receipt of the request filed with the Contracting Authority pursuant to Section 5.15.2, or other period mutually agreed by the parties, the Project Manager shall schedule a meeting to resolve the request and render a decision on the request promptly thereafter or render a decision on the request without a meeting.

Appears in 7 contracts

Samples: dam.assets.ohio.gov, ofcc.ohio.gov, www.utoledo.edu

Meeting with the Project Manager. 5.4.1 Within 30 days after receipt of the request filed with the Contracting Authority Owner pursuant to Section 5.15.2, or other period mutually agreed by the parties, the Project Manager shall schedule a meeting to resolve the request and render a decision on the request promptly thereafter or render a decision on the request without a meeting.

Appears in 4 contracts

Samples: Consultant Agreement, Consultant Agreement, Consultant Agreement

Meeting with the Project Manager. 5.4.1 5.3.1 Within 30 days after receipt of the request filed with the Contracting Authority State pursuant to Section 5.1, or other period mutually agreed by the parties, the Project Manager shall schedule a meeting to resolve the request and render a decision on the request promptly thereafter or render a decision on the request without a meeting.

Appears in 4 contracts

Samples: Consultant Agreement, dam.assets.ohio.gov, ofcc.ohio.gov

AutoNDA by SimpleDocs

Meeting with the Project Manager. 5.4.1 Within 30 days after receipt of the request filed with the Contracting Authority pursuant to Section 5.15.2, or other period mutually agreed by the parties, the Project Manager shall schedule a meeting to resolve the request and render a decision on the request promptly thereafter or render a decision on the request without a meeting.

Appears in 2 contracts

Samples: www.utoledo.edu, ofcc.ohio.gov

Meeting with the Project Manager. 5.4.1 Within 30 days after receipt of the request filed with the Contracting Authority State pursuant to Section 5.15.2, or other period mutually agreed by the parties, the Project Manager shall schedule a meeting to resolve the request and render a decision on the request promptly thereafter or render a decision on the request without a meeting.

Appears in 1 contract

Samples: ofcc.ohio.gov