Common use of MONITORING OF OPERATION AND MAINTENANCE Clause in Contracts

MONITORING OF OPERATION AND MAINTENANCE. ‌ 19.1 Monthly status reports‌ During Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent Engineer. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

MONITORING OF OPERATION AND MAINTENANCE. ‌ 19.1 20.1 Monthly status reports‌ reports 20.1.1 During Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent EngineerAuthority. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

MONITORING OF OPERATION AND MAINTENANCE. ‌ 19.1 Monthly status reports‌ During Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority Participating ULBs and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project Facilities including its compliance or otherwise with the Operation & Maintenance Requirements, Operation & Maintenance Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent Engineer. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 1 contract

Samples: Concession Agreement

MONITORING OF OPERATION AND MAINTENANCE. 19.1 Monthly status reports‌ reports During Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project Road including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent Engineer. In particular, particular such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 1 contract

Samples: Concession Agreement

MONITORING OF OPERATION AND MAINTENANCE. 19.1 Monthly status reports‌ reports 19.1.1 During Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer Expert, a monthly report stating in reasonable detail the condition of the Project including its compliance or otherwise with the Service Requirements, Maintenance Requirements, Maintenance Manual, Service Quality Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent EngineerExpert or the Authority. In particular, particular such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 1 contract

Samples: Concession Agreement

MONITORING OF OPERATION AND MAINTENANCE. ‌ 19.1 Monthly 20.1 Monthly/ Daily status reports‌ reports During Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority MOR and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project Rail System including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent Engineer. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 1 contract

Samples: Construction Agreement

AutoNDA by SimpleDocs

MONITORING OF OPERATION AND MAINTENANCE. 19.1 Monthly status reports‌ reports 19.1.1 During the Operation Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Programme Program and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent EngineerEngineer or the Authority. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 1 contract

Samples: Concession Agreement

MONITORING OF OPERATION AND MAINTENANCE. 19.1 Monthly 16.1 Quarterly status reports‌ During Operation Concession Period, the Concessionaire shall, no later than 7 (seven) days after the close of each monthquarter, furnish to the Concessioning Authority and the Independent Engineer a monthly quarterly report stating in reasonable detail the condition of the Project including its compliance or otherwise with the Maintenance Requirementsmaintenance requirements, Maintenance Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent EngineerAuthority. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 1 contract

Samples: Concession Agreement

MONITORING OF OPERATION AND MAINTENANCE. ‌ 19.1 16.1. Monthly status reports‌ During Operation Concession Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Concessioning Authority and the Independent Engineer a monthly report stating in reasonable detail the condition of the Project Highway including its compliance or otherwise with the Maintenance Requirements, Maintenance Manual, Maintenance Programme and Safety Requirements, and shall promptly give such other relevant information as may be required by the Independent Engineer. In particular, such report shall separately identify and state in reasonable detail the defects and deficiencies that require rectification.

Appears in 1 contract

Samples: Concession Agreement