Net Metering Facility Testing and Maintenance. Customer shall conduct maintenance and testing on its Net Metering Facilities as set forth in the Rule, including but not necessarily limited to R746-312-14. 1.11.1 Customer shall conduct any manufacturer-recommended testing or maintenance at its expense. 1.11.2 Customer shall conduct any post-installation testing, at its expense, necessary to ensure compliance with IEEE standards as set forth in the Rule or to ensure safety. This includes replacing a major equipment component that is different from the originally installed model. 1.11.3 When Customer performs maintenance or testing in accordance with the Rule, it must retain written records documenting the maintenance and results of the testing for three (3) years. 1.11.4 Rocky Mountain Power shall have the right to inspect Customer’s facility after interconnection approval is granted, at reasonable hours and with reasonable prior notice to Customer. If Rocky Mountain Power discovers that the Net Metering Facility is not in compliance with the Rule, Rocky Mountain Power may require Customer to disconnect the Net Metering Facility until compliance is achieved.
Appears in 3 contracts
Samples: Interconnection and Net Metering Service Agreement, Interconnection and Net Metering Service Agreement, Interconnection and Net Metering Service Agreement
Net Metering Facility Testing and Maintenance. Customer shall conduct maintenance and testing on its Net Metering Facilities as set forth in the Rule, including but not necessarily limited to R746-312-14.
1.11.1 Customer shall conduct any manufacturer-recommended testing or maintenance at its expense.
1.11.2 Customer shall conduct any post-installation testing, at its expense, necessary to ensure compliance with IEEE standards as set forth in the Rule or to ensure safety. This includes replacing a major equipment component that is different from the originally installed model.
1.11.3 When Customer performs maintenance or testing in accordance with the Rule, it must retain written records documenting the maintenance and results of the testing for three (3) years.
1.11.4 Rocky Mountain Power shall have the right to inspect Customer’s facility after interconnection approval is granted, at reasonable hours and with reasonable prior notice to Customer. If Rocky Mountain Power discovers that the Net Metering Facility is not in compliance with the Rule, Rocky Mountain Power may require Customer to disconnect the Net Metering Facility until compliance is achieved.Power
Appears in 2 contracts
Samples: Interconnection and Net Metering Service Agreement, Contract for Residential Pv Solar System
Net Metering Facility Testing and Maintenance. Customer shall conduct maintenance and testing on its Net Metering Facilities as set forth in the Rule, including but not necessarily limited to R746-312-14.
1.11.1 1.13.1 Customer shall conduct any manufacturer-recommended testing or maintenance at its expense.
1.11.2 1.13.2 Customer shall conduct any post-installation testing, at its expense, necessary to ensure compliance with IEEE standards as set forth in the Rule or to ensure safety. This includes replacing a major equipment component that is different from the originally installed model.
1.11.3 1.13.3 When Customer performs maintenance or testing in accordance with the Rule, it must retain written records documenting the maintenance and results of the testing for three (3) years.
1.11.4 1.13.4 Rocky Mountain Power shall have the right to inspect Customer’s facility Net Metering Facility after interconnection approval is granted, at reasonable hours and with reasonable prior notice to Customer. If Rocky Mountain Power discovers that the Net Metering Facility is not in compliance with the Rule, Rocky Mountain Power may require Customer to disconnect the Net Metering Facility until compliance is achieved.
Appears in 1 contract
Net Metering Facility Testing and Maintenance. Customer shall conduct maintenance and testing on its Net Metering Facilities as set forth in the Rule, including but not necessarily limited to R746-312-14.
1.11.1 1.12.1 Customer shall conduct any manufacturer-recommended testing or maintenance at its expense.
1.11.2 1.12.2 Customer shall conduct any post-installation testing, at its expense, necessary to ensure compliance with IEEE standards as set forth in the Rule or to ensure safety. This includes replacing a major equipment component that is different from the originally installed model.
1.11.3 1.12.3 When Customer performs maintenance or testing in accordance with the Rule, it must retain written records documenting the maintenance and results of the testing for three (3) years.
1.11.4 1.12.4 Rocky Mountain Power shall have the right to inspect Customer’s facility after interconnection approval is granted, at reasonable hours and with reasonable prior notice to Customer. If Rocky Mountain Power discovers that the Net Metering Facility is not in compliance with the Rule, Rocky Mountain Power may require Customer to disconnect the Net Metering Facility until compliance is achieved.
Appears in 1 contract
Net Metering Facility Testing and Maintenance. Customer shall conduct maintenance and testing on its Net Metering Facilities as set forth in the Rule, including but not necessarily limited to R746-312-14.
1.11.1 1.12.1 Customer shall conduct any manufacturer-recommended testing or maintenance at its expense.
1.11.2 1.12.2 Customer shall conduct any post-installation testing, at its expense, necessary to ensure compliance with IEEE standards as set forth in the Rule or to ensure safety. This includes replacing a major equipment component that is different from the originally installed model.
1.11.3 1.12.3 When Customer performs maintenance or testing in accordance with the Rule, it must retain written records documenting the maintenance and results of the testing for three (3) years.
1.11.4 1.12.4 Rocky Mountain Power shall have the right to inspect Customer’s facility Net Metering Facility after interconnection approval is granted, at reasonable hours and with reasonable prior notice to Customer. If Rocky Mountain Power discovers that the Net Metering Facility is not in compliance with the Rule, Rocky Mountain Power may require Customer to disconnect the Net Metering Facility until compliance is achieved.
Appears in 1 contract