Notice for Initial Energisation of the Interconnection Line. After the submission of the certificate of installation in respect of the Facility and the Seller Interconnection Facilities from the Independent Engineer certifying that the Facility and, Seller Interconnection Facilities has been built in accordance with Schedule A and Schedule D of this Agreement, Seller shall give CEB not less than 5 (five) Business Days’ notice of the time it wishes to first energise the 22 kV interconnection line from CEB to the Facility.