Common use of Notice of Delay Clause in Contracts

Notice of Delay. Within Fourteen (14) days after the date of occurrence of any cause of delay, on account of which the BUILDER claims that it is entitled under this Contract to a postponement of the Delivery Date, the BUILDER shall notify the BUYER in writing or by telefax confirmed in writing of the date when such cause of delay occurred. Likewise, within Fourteen (14) days after the date of ending of such cause of delay, the BUILDER shall notify the BUYER in writing or by xxxxxxx confirmed in writing of the date when such cause of delay ended. The BUILDER shall also notify the BUYER of the period, by which the Delivery Date is postponed by reason of such cause of delay, with all reasonable dispatch after it has been determined. If the BUILDER does not give the timely advice as above, the BUILDER shall lose the right to claim such delays as permissible delay. Failure of the BUYER to acknowledge to the BUILDER’s claim for postponement of the Delivery Date within Fourteen (14) days after receipt by the BUYER of such notice of claim shall be deemed to be a waiver by the BUYER of its right to object to such postponement of the Delivery Date.

Appears in 4 contracts

Samples: Construction Contract, Construction Contract (Danaos Corp), Construction Contract (Danaos Corp)

AutoNDA by SimpleDocs

Notice of Delay. Within Fourteen ten (1410) days after the date BUILDER becomes aware of occurrence of any cause of delaydelay as aforesaid, on account of which the BUILDER claims that it is entitled under this Contract to a postponement of the Delivery Date, the BUILDER shall notify the BUYER in writing or by telefax confirmed in writing by registered mail of the date when such cause of delay occurred. Likewise, within Fourteen ten (1410) days after the date of ending of such cause of delay, the BUILDER shall notify the BUYER in writing or by xxxxxxx telefax confirmed in writing by registered mail of the date when such cause of delay ended. Failure by the BUILDER to give such notice as aforesaid shall prevent the BUILDER to subsequently claim delay on account of such circumstances. The BUILDER shall also notify the BUYER of the period, by which the Delivery Date is postponed by reason of such cause of delay, with all reasonable dispatch despatch after it has been determined. If the BUILDER does not give the timely advice as above, the BUILDER shall lose the right to claim such delays as permissible delay. Failure of the BUYER to acknowledge object to Ulstein Verft AS X.X. Xxx 000, X-0000 Xxxxxxxxxx, Xxxxxx Tel. +00 0000 0000. Fax +00 0000 0000 Ent. No: 912 447 561 xxx.xxxxxxx.xxx the BUILDER’s claim for postponement of the Delivery Date within Fourteen ten (1410) days after receipt by the BUYER of such notice of claim shall be deemed to be a waiver by the BUYER of its right to object to such postponement of the Delivery Date.

Appears in 4 contracts

Samples: Memorandum of Agreement (Nordic American Offshore Ltd.), Memorandum of Agreement (Nordic American Offshore Ltd.), Memorandum of Agreement (Nordic American Offshore Ltd.)

Notice of Delay. Within Fourteen (14) days after the date of occurrence of any cause of delay, on account of which the BUILDER claims that it is entitled under this Contract to a postponement of the Delivery Date, the BUILDER shall notify the BUYER in writing or by telefax confirmed in writing of the date when such cause of delay occurred. Likewise, within Fourteen (14) days after the date of ending of such cause of delay, the BUILDER shall notify the BUYER in writing or by xxxxxxx telefax confirmed in writing of the date when such cause of delay ended. The BUILDER shall also notify the BUYER of the period, by which the Delivery Date is postponed by reason of such cause of delay, with all reasonable dispatch after it has been determined. If the BUILDER does not give the timely advice as above, the BUILDER shall lose the right to claim such delays as permissible delay. Failure of the BUYER to acknowledge to the BUILDER’s claim for postponement of the Delivery Date within Fourteen (14) days after receipt by the BUYER of such notice of claim shall be deemed to be a waiver by the BUYER of its right to object to such postponement of the Delivery Date.

Appears in 3 contracts

Samples: Construction Contract (Danaos Corp), Construction Contract (Danaos Corp), Construction Contract (Danaos Corp)

Notice of Delay. Within Fourteen Ten (1410) days after the date of occurrence of any cause of delay, on account of which the BUILDER claims that it is entitled under this Contract to a postponement of the Delivery Date, the BUILDER shall notify the BUYER in writing or by telefax confirmed in writing of the date when such cause of delay occurred. Likewise, within Fourteen Ten (1410) days after the date of ending of such cause of delay, the BUILDER shall notify the BUYER in writing or by xxxxxxx telefax confirmed in writing of the date when such cause of delay ended. The BUILDER shall also notify promptly the BUYER of the period, by which in their opinion the Delivery Date is postponed by reason of such cause of delay, with all reasonable dispatch after it has been determined. If the BUILDER does not give the timely advice as above, the BUILDER shall lose the right to claim such delays as permissible delay. Failure of the BUYER to acknowledge to the BUILDER’s 'S claim for postponement of the Delivery Date within Fourteen Ten (1410) days after receipt by the BUYER of such notice of claim shall be deemed to be a waiver by the BUYER of its right to object to such postponement of the Delivery Date.

Appears in 2 contracts

Samples: Construction Contract (DryShips Inc.), Construction Contract (DryShips Inc.)

AutoNDA by SimpleDocs

Notice of Delay. Within Fourteen (14) days after the date of occurrence of any cause of delay, on account of which the BUILDER claims that it is entitled under this Contract to a postponement of the Delivery Date, the BUILDER shall notify the BUYER OWNER in writing or by telex or telefax confirmed in writing of the date when such cause of delay occurred. Likewise, within Fourteen (14) days after the date of ending of such cause of delay, the BUILDER shall notify the BUYER OWNER in writing or by xxxxxxx telex or telefax confirmed in writing of the date when such cause of delay ended. The BUILDER shall also notify promptly the BUYER OWNER of the period, by which the Delivery Date is postponed by reason of such cause of delay, with all reasonable dispatch after it has been determined. If the BUILDER does not give the timely advice as above, the BUILDER shall lose the right to claim such delays as permissible delay. Failure of the BUYER OWNER to acknowledge to the BUILDER’s 's claim for postponement of the Delivery Date within Fourteen fourteen (14) days after receipt by the BUYER OWNER of such notice of claim shall be deemed to be a waiver by the BUYER OWNER of its right to object to such postponement of the Delivery Date.

Appears in 2 contracts

Samples: Construction Contract (R&b Falcon Corp), Contract for Construction and Sale of Vessel (R&b Falcon Corp)

Notice of Delay. Within Fourteen (14) days after the date of occurrence of any cause of delay, on account of which the BUILDER claims that it is entitled under this Contract to a postponement of the Delivery Date, the BUILDER shall notify the BUYER in writing or by telex or telefax confirmed in writing of the date when such cause of delay occurred. Likewise, within Fourteen (14) days after the date of ending of such cause of delay, the BUILDER shall notify the BUYER in writing or by xxxxxxx telex confirmed in writing of the date when such cause of delay ended. The BUILDER shall also notify promptly the BUYER of the period, by which the Delivery Date is postponed by reason of such cause of delay, with all reasonable dispatch after it has been determined. If the BUILDER does not give the timely advice as above, the BUILDER shall lose the right to claim such delays as permissible delay. Failure of the BUYER to acknowledge to the BUILDER’s 's claim for postponement of the Delivery Date within Fourteen (14) days after receipt by the BUYER of such notice of claim shall be deemed to be a waiver by the BUYER of its right to object to such postponement of the Delivery Date.

Appears in 1 contract

Samples: Contract for Construction and Sale of a Drilling Ship (R&b Falcon Corp)