Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Provider, Distribution Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Provider's Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.
Appears in 24 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Transmission Provider, Distribution Transmission Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution Transmission Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.
Appears in 13 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Qualifying Facility Large Generator Interconnection Agreement, Qualifying Facility Large Generator Interconnection Agreement
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution ProviderTransmission Owner, Distribution Provider Transmission Owner shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Provider's Transmission Owner’s Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.25.1.1. Distribution Provider Transmission Owner and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.
Appears in 11 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Transmission Provider, Distribution Transmission Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Transmission Provider's ’s Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution Transmission Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.
Appears in 5 contracts
Samples: Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Provider, Distribution Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Provider's Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.
Appears in 5 contracts
Samples: Clustering Large Generator Interconnection Agreement (Clgia), Service Agreement for Wholesale Distribution Service, Generator Interconnection Agreement (Gia)
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Provider, Distribution Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Provider's Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.to
Appears in 2 contracts
Samples: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Transmission Provider, Distribution Transmission Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Transmission Provider's Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution .. Transmission Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement (Lgia)
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Transmission Provider, Distribution Transmission Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Transmission Provider's ’s Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution Transmission Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.
Appears in 1 contract
Option to Build. If the dates designated by Interconnection Customer are not acceptable to Distribution Provider, Distribution Provider shall so notify Interconnection Customer within thirty (30) Calendar Days, and unless the Parties agree otherwise, Interconnection Customer shall have the option to assume responsibility for the design, procurement and construction of Distribution Provider's Interconnection Facilities and Stand Alone Network Upgrades on the dates specified in Article 5.1.2. Distribution Provider and Interconnection Customer must agree as to what constitutes Stand Alone Network Upgrades and identify such Stand Alone Network Upgrades in Appendix A. Except for Stand Alone Network Upgrades, Interconnection Customer shall have no right to construct Network Upgrades under this option. This provision only applies to Generating Facilities larger than 20 MW.option.
Appears in 1 contract
Samples: Clustering Large Generator Interconnection Agreement and Distribution Service Agreement