Other TxDOT Approvals. 6.3.4.1 Whenever the CDA Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness.
6.3.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 6.3.2, then Developer may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay from and after lapse of the applicable time period under Section 6.3.2 may constitute TxDOT-Caused Delay for which Developer may be entitled to issue a Relief Event Notice and Compensation Event Notice under Sections 13.1 and 13.2.
Other TxDOT Approvals. 3.1.4.1 Whenever the Contract Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness.
3.1.4.2 If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, Texas Department of Transportation SH 249 Extension Project 18 Request for Proposals Design-Build Agreement September 28, 2016 determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor may be entitled to submit a Claim in accordance with Section 13.3.
Other TxDOT Approvals. 3.1.4.1. Whenever the DBA Documents indicate that a Submittal or other matter is subject to TxDOT’s approval or consent and no particular standard therefor is stated, then the standard shall be reasonableness.
3.1.4.2. If the reasonableness standard applies to TxDOT’s right of approval of or consent to a Submittal, and TxDOT delivers no approval, consent, determination, decision or other action within the applicable time period under Section 3.1.2, then DB Contractor may deliver to TxDOT a written notice stating the date within which TxDOT was to have decided or acted and that if TxDOT does not decide or act within five Business Days after receipt of the notice, delay thereafter may constitute a TxDOT-Caused Delay for which DB Contractor may be entitled to submit a Claim in accordance with Section 13.3.1.
Other TxDOT Approvals