Payments for Variations Sample Clauses

Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. 40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work. 40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs. 40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event. 40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
AutoNDA by SimpleDocs
Payments for Variations. 38.1. There shall be an order in writing to execute the extra item of work from the Employer. Extra item can be additional, substituted or altered item depending on their relation to the original item. 38.2. Rates for the extra item shall be worked out as below: (i) In the case of extra items, if accepted rates for identical item are available in the contract the same shall be taken. (ii) In the case of extra items for which similar item exist in the contract, the rates shall be derived from the original item by appropriate adjustment of cost of affected components. (iii) In the case of extra items for which similar items do not exist in the contract and rate exist in the standard schedule of rates, the rates shall be arrived based on standard data rate prevalent at the time of ordering the extra item after applying the overall tender variation. However, no tender excess will be applied. (iv) In the case of extra items for which standard data is not available and that do not come in the category mentioned in (i), (ii) and (iii) above, the rates shall be worked by the Engineer based on prevailing market rates giving due consideration to the analysis of rates and data furnished by the contractor. 38.3. The Contractor shall not be entitled to additional payment for costs which could have been avoided by giving early warning.
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. 40.2 Deleted. 40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with the quotation within a reasonable time specified by the Engineer in accordance with Clause 40.1) the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs. 40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event. 40.5 The Contractor shall not be entitled to additional payment for costs which could have been avoided by giving early warning.
Payments for Variations. 43.1 The Contractor shall provide the Project Manager with a quotation for carrying out the Variation when requested to do so by the Project Manager. The Project Manager shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Project Manager and before the Variation is ordered.
Payments for Variations. If the Customer requests the Provider in writing to alter or vary the Services, and the Provider has agreed to render those services, the amount payable by the Customer to the Provider for any variation carried out in accordance with such direction, will be as agreed by the parties.
Payments for Variations. 48.1 The Contractor shall provide the Project Manager with a quotation for carrying out the Variation when requested to do so by the Project Manager. The Project Manager shall assess the quotation, which shall be given within seven (7) days of the request or within any longer period stated by the Project Manager and before the Variation is ordered. 48.2 If the work in the variation corresponds with an item description in the Xxxx of Quantities and if, in the opinion of the Project Manager, the quantity of work above the limit stated in Sub-Clause 38 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the Xxxx of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Xxxx of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work. 48.3 If the Contractor’s quotation is unreasonable, the Project Manager may order the Variation and make a change to the contract price, which shall be based on the Project Manager’s own forecast of the effects of the Variation on the Contractor’s costs. 48.4 If the Project Manager decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event. 48.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation [withbreakdown of unit rates]for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. 40.2 If the work in the Variation corresponds with an item description in the Xxxx of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub-Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the Xxxx of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Xxxx of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work. 40.3 If the Contractor’s quotation is unreasonable, [or if contractor fails to provide the Engineer with a quotation within a reasonable time specified by Engineer in accordance with GCC40.1] the Engineer may order the
AutoNDA by SimpleDocs
Payments for Variations. If rates for Variation items are specified in the Bill of Quantities, the Contractor shall carry out such work at the same rate.
Payments for Variations. The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. 40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or 40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1), the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs. 40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event. 40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!