Performance of the Works. 7.1 The Contractor shall perform the Works in accordance with: (a) Prudent Engineering and Construction Practice (including in the international maritime and oil and gas industries); (b) the requirements of the Classification Society; (c) the Specifications; (d) Applicable Laws; (e) the rules, regulations and requirements of the Regulatory Body as at the Date of Agreement; and (f) any other requirements of this Agreement. 7.2 Without prejudice to the generality of Article 7.1 (Performance of the Works), the Contractor shall be responsible for the conduct of the Works and shall: (a) provide suitably qualified and competent personnel; and (b) to the extent not otherwise expressly provided for: (i) in this Agreement, perform the Works in a manner consistent with relevant International Standards (which shall be selected by the Contractor); and (ii) in the GIMI Topsides Agreement, procure that the Sub-Contractor performs the Sub-Contract Works in a manner consistent with International Standards (which shall be selected by the Sub-Contractor); (c) be responsible for the adequacy of the HSSE standards in accordance with the HSSE Plan (to the extent applicable to the Works) that is to be implemented in connection with the performance of the Works. 7.3 The Sub-Contractor shall perform the Sub-Contract Works. The Owner shall co-operate with the Contractor in the efficient and timely performance of this Agreement and the GIMI Topsides Agreement so as to avoid any unnecessary cost or expense to the Contractor and any unnecessary impact on the Works. 7.4 The Owner recognises and accepts that the Contractor is reliant on the Owner-nominated Sub-Contractor for the performance of the Sub-Contract Works and does not have the capability to perform the Sub-Contract Works itself. It is the intention of the Parties that the Contractor does not undertake any of the obligations of the Sub-Contractor under the GIMI Topsides Agreement, but that the Works shall include but not be limited to the management and co-ordination of the Sub-Contract Works, including expediting the Sub-Contractor and the assembly, installation and integration of the Equipment in accordance with Prudent Engineering and Construction Practice. 7.5 All equipment and materials supplied by the Contractor in the performance of its obligations under this Agreement shall be new and unused (unless agreed otherwise), originally manufactured with certificates of quality and of the Classification Society where normally available. 7.6 All old parts and equipment of the Vessel shall remain the property of the Owner and may be removed by the Owner if it wishes. All materials scrapped except the shaft and propeller shall become the property of the Contractor.
Appears in 2 contracts
Samples: Engineering, Procurement & Construction Contract, Engineering, Procurement & Construction Contract (Golar LNG LTD)
Performance of the Works. 7.1 6.1 The Contractor shall perform the Works in accordance with:
(a) Prudent Engineering and Construction Practice (including in the international maritime and oil and gas industries)Practice;
(b) within the requirements rules of the Classification SocietySociety as modified by Appendix 1B;
(c) the Specifications;
(d) Applicable LawsLaws as at the Date of Agreement;
(e) the rules, regulations and requirements of the Regulatory Body Flag State Registry as at the Date of Agreement; and
(f) and any other requirements of this Agreement.
7.2 Without prejudice to the generality of Article 7.1 (Performance of the Works), the Contractor shall be responsible for the conduct of the Works and shall:
(a) provide suitably qualified and competent personnel; and
(b) to the extent not otherwise expressly provided for:
(i) in this Agreement, perform the Works in a manner consistent with relevant International Standards (which shall be selected by the Contractor); and
(ii) in the GIMI Topsides Agreement, procure that the Sub-Contractor performs the Sub-Contract Works in a manner consistent with International Standards (which shall be selected by the Sub-Contractor);
(c) be responsible for the adequacy of the HSSE standards in accordance with the HSSE Plan (to the extent applicable to the Works) that is to be implemented in connection with the performance of the Works.
7.3 . The Sub-Contractor shall perform the Sub-Contract Works. The Owner shall co-operate with the Contractor in the efficient and timely performance of this Agreement and the GIMI GANDRIA Topsides Agreement so as to avoid any unnecessary cost or expense to the Contractor and any unnecessary impact on the Works.
7.4 6.2 The Owner recognises and accepts that the Contractor is reliant on the Owner-nominated Sub-Contractor for the performance of the Sub-Contract Works and does not have the capability to perform the Sub-Contract Works itself. It is the intention of the Parties that the Contractor does not undertake any of the obligations of the Sub-Contractor under the GIMI GANDRIA Topsides Agreement, but that the Works shall include but not be limited to the management and co-ordination of the Sub-Contract Works, including expediting the Sub-Contractor and the assembly, installation and integration of the Equipment in accordance with Prudent Engineering and Construction Practice.
7.5 6.3 All equipment and materials supplied by the Contractor in the performance of its obligations under this Agreement shall be new and unused (unless agreed otherwise), originally manufactured with certificates of quality and of the Classification Society where normally available. The Contractor shall obtain certificates of the Classification Society where normally available in respect of the Contractor’s Scope.
7.6 6.4 All old parts and equipment of the Vessel shall remain the property of the Owner and may be removed by the Owner if it wishes. All materials scrapped except the shaft and propeller shall become the property of the Contractor.
Appears in 2 contracts
Samples: Engineering, Procurement & Construction Contract, Engineering, Procurement & Construction Contract (Golar LNG LTD)
Performance of the Works. 7.1 6.1 The Contractor shall perform the Works in accordance with:
(a) Prudent Engineering and Construction Practice (including in the international maritime and oil and gas industries)Practice;
(b) within the requirements rules of the Classification SocietySociety as modified by Appendix 1B;
(c) the Specifications;
(d) Applicable LawsLaws as at the Date of Agreement;
(e) the rules, regulations and requirements of the Regulatory Body Flag State Registry as at the Date of Agreement; and
(f) and any other requirements of this Agreement.
7.2 Without prejudice to the generality of Article 7.1 (Performance of the Works), the Contractor shall be responsible for the conduct of the Works and shall:
(a) provide suitably qualified and competent personnel; and
(b) to the extent not otherwise expressly provided for:
(i) in this Agreement, perform the Works in a manner consistent with relevant International Standards (which shall be selected by the Contractor); and
(ii) in the GIMI Topsides Agreement, procure that the Sub-Contractor performs the Sub-Contract Works in a manner consistent with International Standards (which shall be selected by the Sub-Contractor);
(c) be responsible for the adequacy of the HSSE standards in accordance with the HSSE Plan (to the extent applicable to the Works) that is to be implemented in connection with the performance of the Works.
7.3 . The Sub-Contractor shall perform the Sub-Contract Works. The Owner shall co-operate with the Contractor in the efficient and timely performance of this Agreement and the GIMI Topsides Agreement so as to avoid any unnecessary cost or expense to the Contractor and any unnecessary impact on the Works.
7.4 6.2 The Owner recognises and accepts that the Contractor is reliant on the Owner-nominated Sub-Contractor for the performance of the Sub-Contract Works and does not have the capability to perform the Sub-Contract Works itself. It is the intention of the Parties that the Contractor does not undertake any of the obligations of the Sub-Contractor under the GIMI Topsides Agreement, but that the Works shall include but not be limited to the management and co-ordination of the Sub-Contract Works, including expediting the Sub-Contractor and the assembly, installation and integration of the Equipment in accordance with Prudent Engineering and Construction Practice.
7.5 6.3 All equipment and materials supplied by the Contractor in the performance of its obligations under this Agreement shall be new and unused (unless agreed otherwise), originally manufactured with certificates of quality and of the Classification Society where normally available. The Contractor shall obtain certificates of the Classification Society where normally available in respect of the Contractor’s Scope.
7.6 6.4 All old parts and equipment of the Vessel shall remain the property of the Owner and may be removed by the Owner if it wishes. All materials scrapped except the shaft and propeller shall become the property of the Contractor.
Appears in 1 contract
Samples: Engineering, Procurement & Construction Contract (Golar LNG LTD)
Performance of the Works. 7.1 4.1 The Contractor shall perform the Works in accordance with:
(a) Prudent Engineering and Construction Practice (including in the international maritime and oil and gas industries)Practice;
(b) within the requirements rules of the Classification SocietySociety as modified by Appendix 1B;
(c) the Specifications;
(d) Applicable LawsLaws as at the Date of Agreement;
(e) the rules, regulations and requirements of the Regulatory Body Flag State Registry as at the Date of Agreement; and
(f) and any other requirements of this Agreement.
7.2 Without prejudice to the generality of Article 7.1 (Performance of the Works), the Contractor shall be responsible for the conduct of the Works and shall:
(a) provide suitably qualified and competent personnel; and
(b) to the extent not otherwise expressly provided for:
(i) in this Agreement, perform the Works in a manner consistent with relevant International Standards (which shall be selected by the Contractor); and
(ii) in the GIMI Topsides Agreement, procure that the Sub-Contractor performs the Sub-Contract Works in a manner consistent with International Standards (which shall be selected by the Sub-Contractor);
(c) be responsible for the adequacy of the HSSE standards in accordance with the HSSE Plan (to the extent applicable to the Works) that is to be implemented in connection with the performance of the Works.
7.3 . The Sub-Contractor shall perform the Sub-Contract Works. The Owner shall co-operate with the Contractor in the efficient and timely performance of this Agreement and the GIMI Topsides Agreement so as to avoid any unnecessary cost or expense to the Contractor and any unnecessary impact on the Works.
7.4 4.2 The Owner recognises and accepts that the Contractor is reliant on the Owner-nominated Sub-Contractor for the performance of the Sub-Contract Works and does not have the capability to perform the Sub-Contract Works itself. It is the intention of the Parties that the Contractor does not undertake any of the obligations of the Sub-Contractor under the GIMI Topsides Agreement, but that the Works shall include but not be limited to the management and co-ordination of the Sub-Contract Works, including expediting the Sub-Contractor and the assembly, installation and integration of the Equipment in accordance with Prudent Engineering and Construction Practice.
7.5 4.3 All equipment and materials supplied by the Contractor in the performance of its obligations under this Agreement shall be new and unused (unless agreed otherwise), originally manufactured with certificates of quality and of the Classification Society where normally available. The Contractor shall obtain certificates of the Classification Society where normally available in respect of the Contractor’s Scope.
7.6 4.4 All old parts and equipment of the Vessel shall remain the property of the Owner and may be removed by the Owner if it wishes. All materials scrapped except the shaft and propeller shall become the property of the Contractor.
Appears in 1 contract
Samples: Engineering, Procurement & Construction Contract (Golar LNG LTD)
Performance of the Works. 7.1 Owner: ______ Contractor: ______
6.1 The Contractor shall perform the Works in accordance with:
(a) Prudent Engineering and Construction Practice (including in the international maritime and oil and gas industries)Practice;
(b) within the requirements rules of the Classification SocietySociety as modified by Appendix 1B;
(c) the Specifications;
(d) Applicable LawsLaws as at the Date of Agreement;
(e) the rules, regulations and requirements of the Regulatory Body Flag State Registry as at the Date of Agreement; and
(f) and any other requirements of this Agreement.
7.2 Without prejudice to the generality of Article 7.1 (Performance of the Works), the Contractor shall be responsible for the conduct of the Works and shall:
(a) provide suitably qualified and competent personnel; and
(b) to the extent not otherwise expressly provided for:
(i) in this Agreement, perform the Works in a manner consistent with relevant International Standards (which shall be selected by the Contractor); and
(ii) in the GIMI Topsides Agreement, procure that the Sub-Contractor performs the Sub-Contract Works in a manner consistent with International Standards (which shall be selected by the Sub-Contractor);
(c) be responsible for the adequacy of the HSSE standards in accordance with the HSSE Plan (to the extent applicable to the Works) that is to be implemented in connection with the performance of the Works.
7.3 . The Sub-Contractor shall perform the Sub-Contract Works. The Owner shall co-operate with the Contractor in the efficient and timely performance of this Agreement and the GIMI Topsides Agreement so as to avoid any unnecessary cost or expense to the Contractor and any unnecessary impact on the Works.
7.4 6.2 The Owner recognises and accepts that the Contractor is reliant on the Owner-nominated Sub-Contractor for the performance of the Sub-Contract Works and does not have the capability to perform the Sub-Contract Works itself. It is the intention of the Parties that the Contractor does not undertake any of the obligations of the Sub-Contractor under the GIMI Topsides Agreement, but that the Works shall include but not be limited to the management and co-ordination of the Sub-Contract Works, including expediting the Sub-Contractor and the assembly, installation and integration of the Equipment in accordance with Prudent Engineering and Construction Practice.
7.5 6.3 All equipment and materials supplied by the Contractor in the performance of its obligations under this Agreement shall be new and unused (unless agreed otherwise), originally manufactured with certificates of quality and of the Classification Society where normally available. The Contractor shall obtain certificates of the Classification Society where normally available in respect of the Contractor’s Scope.
7.6 6.4 All old parts and equipment of the Vessel shall remain the property of the Owner and may be removed by the Owner if it wishes. All materials scrapped except the shaft and propeller shall become the property of the Contractor.
Appears in 1 contract
Samples: Engineering, Procurement & Construction Contract (Golar LNG LTD)