Performance Test Requirements Sample Clauses

Performance Test Requirements. Contractor shall perform the Work so the Plant satisfies the performance criteria for Performance Test prior to, and as a condition of, Biogas Substantial Completion or Substantial Completion, as applicable (in each case, in accordance with, and as set forth in Annex 18, the Testing Protocols).
AutoNDA by SimpleDocs

Related to Performance Test Requirements

  • Performance Tests Contractor shall perform Performance Tests in accordance with Section 11.2 of the Agreement and Attachment S.

  • Performance Testing 7.2.1 The Design-Builder shall direct and supervise the tests and, if necessary, the retests of the Plant using Design-Builder’s supervisory personnel and the Air Emissions Tester shall conduct the air emissions test, in each case, in accordance with the testing procedures set forth in Exhibit A (the “Performance Tests”), to demonstrate, at a minimum, compliance with the Performance Guarantee Criteria. Owner is responsible for obtaining Air Emissions Tester and for ensuring Air Emissions Tester’s timely performance. Design-Builder shall cooperate with the Air Emissions Tester to facilitate performance of all air emissions tests. Design-Builder shall not be held responsible for the actions of Owner’s employees and third parties involved in the Performance Testing, including but not limited to Air Emissions Tester. 7.2.2 No later than thirty (30) Days prior to the earlier of the Scheduled Substantial Completion Date or Substantial Completion, Design-Builder shall provide to Owner for review a detailed testing plan for the Performance Tests (other than for air emissions). Owner and Design-Builder shall agree upon a testing plan that shall be consistent with the Performance Test Protocol contained in Exhibit A hereto. After such agreement has been reached, Design-Builder shall notify the Owner five (5) business days prior to the date Design-Builder intends to commence the Performance Tests and shall notify the Owner upon commencement of the Performance Tests. Owner and Independent Engineer each have the right to witness all testing, including the Performance Tests and any equipment testing, whether at the Site or at the Subcontractor’s or equipment supplier’s premises during the course of this Agreement. Notwithstanding the foregoing sentence, Owner shall bear the costs of providing a witness to any such testing and all such witnesses shall comply at all times with Design-Builder’s, Subcontractor’s or equipment supplier’s safety and security procedures and other reasonable requirements, and otherwise conduct themselves in a manner that does not interfere with Design-Builder’s, Subcontractor’s or equipment supplier’s activities or operations. 7.2.3 Design-Builder shall provide to Owner a Performance Test report (excluding results from air emissions testing), including all applicable test data, calculations and certificates indicating the results of the Performance Tests and, within five (5) business days of Owner’s receipt of such results, Owner, Independent Engineer and Design-Builder will jointly inspect such Work and review the results of the Performance Tests to verify that the Performance Guarantee Criteria have been met. If Owner or Independent Engineer reasonably determines that the Performance Guarantee Criteria have not been met, Owner shall notify Design-Builder the reasons why Owner determined that the Performance Guarantee Criteria have not been met and Design-Builder shall promptly take such action or perform such additional work as will achieve the Performance Guarantee Criteria and shall issue to the Owner another notice in accordance with Section 7.2.2; provided however that if the notice relates to a retest, the notice may be provided no less than two (2) business days prior to the Performance Tests. Such procedure shall be repeated as necessary until Owner and Independent Engineer verifies that the Performance Guarantee Criteria have been met. 7.2.4 If Owner, for whatever reason, prevents Design-Builder from demonstrating the Performance Guarantee Criteria within thirty (30) Days of Design-Builder’s notice that the Plant is ready for Performance Testing, then Design-Builder shall be excused from demonstrating compliance with the Performance Guarantee Criteria during such period of time that Design-Builder is prevented from demonstrating compliance with the Performance Guarantee Criteria; provided however that Design-Builder will be deemed to have fulfilled all of its obligations to demonstrate that the Plant meets the Performance Guarantee Criteria should such period of time during which Design-Builder is prevented from demonstrating the Performance Criteria exceed thirty (30) Days or extend beyond the Final Completion Date.

  • Performance Requirements A. There is no guaranteed minimum amount of work which will be ordered under this Contract. B. The total Contract amount will not exceed $4,900,000. C. This is a Contract for work specified in individual Job Orders. Work ordered prior to but not completed by the expiration of the Contract period, and any additional work required as a result of unforeseen conditions encountered during construction up to six (6) months after the contract expiration date, will be completed with all provisions of this Contract still in force. Performance time for each Job Order issued under this Contract will be determined in accordance with the Contract. This performance time will be determined and agreed upon by both Parties for each individual Job Order. Contractor must self-perform 20% of the Work under this Contract for ‘A’ and ‘B’ licenses. Contractor must self-perform 75% of the Work under this Contract, unless otherwise approved by the County, for ‘C’ licenses. D. This is an indefinite-quantity Contract for the supplies or services specified and effective for the period stated. Work or performance shall be made only as authorized by Job Orders issued in accordance with the ordering procedures clause. The Contractor agrees to furnish to the County when and if ordered, the supplies or services specified in the Contract up to and including the quantity designated in the Job Orders issued as the maximum designated in the Contract.

  • Project Requirements 1. Project must conform to regulations under 24 CFR Part 92, commonly known as the HOME Regulations.

  • Performance Standards The Contractor agrees to perform all tasks and provide deliverables as set forth in the Contract. The Department and the Customer will be entitled at all times, upon request, to be advised as to the status of work being done by the Contractor and of the details thereof.

  • Service Requirement Except as otherwise provided in Section 6(e) of the Plan or Section 2 of this Agreement, this Option may be exercised only while you continue to provide Service to the Company or any Affiliate, and only if you have continuously provided such Service since the Grant Date of this Option.

  • Performance Standard The Department’s Grant Manager will review the documentation to verify that the deliverables have been completed as described above. Upon review and written acceptance by the Department’s Grant Manager, the Grantee may proceed with payment request submittal. Payment Request Schedule: The Grantee may submit a payment request for cost reimbursement no more frequently than monthly.

  • Subcontract Requirements As required by Section 6.22(e)(5) of the Administrative Code, Contractor shall insert in every subcontract or other arrangement, which it may make for the performance of Covered Services under this Agreement, a provision that said subcontractor shall pay to all persons performing labor in connection with Covered Services under said subcontract or other arrangement not less than the highest general prevailing rate of wages as fixed and determined by the Board of Supervisors for such labor or services.

  • Performance Levels (a) The Performance Levels which apply to the performance by the respective Parties of their obligations under this Agreement are set out in Part 1 of Schedule 5. A failure by either Party to achieve the relevant Performance Level will not constitute a breach of this Agreement and the only consequences of such failure as between the Parties shall be the consequences set out in this Clause 5.6. (b) If the Operator does not comply with the Operator Performance Level then the Access Holder must pay to QR Network the amount determined in accordance with Schedule 5 as part of the invoice issued by QR Network for Access Charges and other charges for the Billing Period immediately following QR Network becoming entitled to that amount. Where there is no next Billing Period, the Operator must pay such amount to QR Network within fourteen (14) days after receipt of a Tax Invoice from QR Network. (c) If QR Network does not comply with the QR Network Performance Level then QR Network will credit to the Access Holder the amount determined in accordance with Schedule 5 by way of a deduction from the invoice issued by QR Network for Access Charges and other charges for the Billing Period immediately following the Access Holder becoming entitled to that amount. Where there is no next Billing Period, QR Network must pay such amount to the Access Holder within fourteen (14) days after receipt of a Tax Invoice from the Access Holder. (d) The Parties must, if requested by either Party, meet to review the Performance Levels subject to such review not occurring within six (6) Months after the Commitment Date or any previous review of the Performance Levels. If either Party notifies the other that it considers that the Performance Levels are no longer appropriate, the Parties may agree on varied Performance Levels and any associated variations to the Agreement including the Base Access Charges and the Train Service Description. If the Parties are unable to agree to such variations, then the existing Performance Levels shall continue to apply unless varied by QR Network in accordance with the provisions of Clause 5.6(e). (e) In the event that the Access Holder and/or the Operator (i) does not comply in any material respect with the Train Service Description; and (ii) the Access Holder fails to demonstrate to the reasonable satisfaction of QR Network when requested to do so, that the Access Holder will consistently comply with the Train Service Description for the remainder of the Term then, following consultation with the Access Holder, QR Network will be entitled to: (iii) vary the Train Service Description to a level it reasonably expects to be achievable by the Access Holder for the remainder of the Term having regard to the extent of previous compliance with the Train Service Description (ignoring, for the purpose of assessing previous compliance, any non-compliance to the extent that the non-compliance was attributable to a Railway Operator (other than the Access Holder) or to QR Network); and (iv) vary the Agreement (including, without limitation, the Operator Performance Level and the Base Access Charges) to reflect the impact of the change in the Train Service Description. (f) The Access Holder shall be entitled to dispute any variation proposed by QR Network pursuant to Clause 5.6(e) and such dispute will be referred to an expert for resolution in accordance with Clause 17.3.

  • Basic Requirements To be eligible for PayPal’s Seller Protection program, all of the following basic requirements must be met, as well as any applicable additional requirements: • The primary address for your PayPal account must be in the United States. • The item must be a physical, tangible good that can be shipped, except for items subject to the Intangible Goods Additional Requirements. Transactions involving items that you deliver in person in connection with payment made in your physical store, may also be eligible for PayPal’s Seller Protection program so long as the buyer paid for the transaction in person by using a PayPal goods and services QR code. • You must ship the item to the shipping address on the Transaction Details page in your PayPal account for the transaction. If you originally ship the item to the recipient’s shipping address on the Transaction Details page but the item is later redirected to a different address, you will not be eligible for PayPal’s Seller Protection program. We therefore recommend not using a shipping service that is arranged by the buyer, so that you will be able to provide valid proof of shipping and delivery. • The shipping requirement does not apply to eligible transactions involving items that you deliver in person; provided, however, that you agree to provide us with alternative evidence of delivery or such additional documentation or information relating to the transaction that we may request. • You must respond to PayPal’s requests for documentation and other information in a timely manner as requested in our email correspondence with you or in our correspondence with you through the Resolution Center. If you do not respond to PayPal’s request for documentation and other information in the time requested, you may not be eligible for PayPal’s Seller Protection program. • If the sale involves pre-ordered or made-to-order goods, you must ship within the timeframe you specified in the listing. Otherwise, it is recommended that you ship all items within 7 days after receipt of payment. • You provide us with valid proof of shipment or delivery. • The payment must be marked “eligible” or “partially eligible” in the case of Unauthorized Transaction claims, or “eligible” in the case of Item Not Received claims, for PayPal’s Seller Protection program on the Transaction Details page. • In the case of an Unauthorized Transaction claim, you must provide valid proof of shipment or proof of delivery that demonstrates that the item was shipped or provided to the buyer no later than two days after PayPal notified you of the dispute or reversal. For example, if PayPal notifies you of an Unauthorized Transaction claim on September 1, the valid proof of shipment must indicate that the item was shipped to the buyer no later than September 3 to be eligible for PayPal’s Seller Protection program. PayPal determines, in its sole discretion, whether your claim is eligible for PayPal’s Seller Protection program. PayPal will make a decision, in its sole discretion, based on the eligibility requirements, any information or documentation provided during the resolution process, or any other information PayPal deems relevant and appropriate under the circumstances. To be eligible for PayPal’s Seller Protection program for a buyer’s Item Not Received claim, you must meet both the basic requirements and the additional requirements listed below: • Where a buyer files a chargeback with the issuer for a card-funded transaction, the payment must be marked “eligible” for PayPal’s Seller Protection on the Transaction Details page. • You must provide proof of delivery as described below.