Physical Change. Forest Service shall adjust the Specified Road construction cost if, prior to acceptance under BT6.36, a physical change, caused by a single event and not due to negligence of Purchaser, results in an increase or decrease in work and/or materials furnished by Purchaser involving additional estimated cost of:
Appears in 59 contracts
Samples: Timber Sale Contract, Timber Sale Contract, Timber Sale Contract
Physical Change. (a) Forest Service shall adjust the Specified Road construction cost if, prior to acceptance under BT6.36G.3.6, a physical change, caused by a single event and not due to negligence of PurchaserContractor, results in an increase or decrease in work and/or materials furnished by Purchaser Contractor involving additional estimated cost of:
(i) More than $10,000 or
(ii) More than 10 percent of total Specified Road construction cost, whichever is less.
Appears in 15 contracts
Samples: Integrated Resource Contract, Integrated Resource Contract, Integrated Resource Contract
Physical Change. (a) Forest Service shall adjust the Specified Road construction cost if, prior to acceptance under BT6.36G.3.6, a physical change, caused by a single event and not due to negligence of PurchaserContractor, results in an increase or decrease in work and/or materials furnished by Purchaser Contractor involving additional estimated cost of:
Appears in 5 contracts
Samples: Integrated Resource Contract, Integrated Resource Contract, Integrated Resource Contract