Planned Outages. No later than fifteen (15) Business Days prior to the end of each year during the Term, Seller shall provide to Buyer a Planned Outage schedule for the upcoming year. Seller shall provide Buyer with reasonable advance notice of any material change in the Planned Outage schedule. Seller shall determine the number and extent of Planned Outages in a Commercially Reasonable Xxxxxx recognizing that it is the intent of the Parties to maximize production of the Facility and to such extent Seller shall be excused from providing the Product during such Planned Outage(s). Unless both Parties expressly agree otherwise, any Planned Outage shall only occur during the months of March, April, May, September, October, or November.
Appears in 8 contracts
Samples: Power Purchase Agreement, Renewable Power Purchase Agreement, Renewable Power Purchase Agreement