Common use of Preliminary Schedule Clause in Contracts

Preliminary Schedule. Unless otherwise stated in Exhibit 1, within fifteen (15) days of Design-Builder’s receipt of Department’s Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Preliminary Schedule in accordance with Exhibit 11.1 (Special Provision for Design-Build Schedules). The Preliminary Schedule shall be the basis for monitoring the Design-Builder’s performance of the Work until such time as a Baseline Schedule has been approved by Department in accordance with Section 11.1.2 below. Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Preliminary Schedule.

Appears in 3 contracts

Samples: Lump Sum Design Build Agreement, Lump Sum Design Build Agreement, Lump Sum Design Build Agreement

AutoNDA by SimpleDocs

Preliminary Schedule. Unless otherwise stated in Exhibit 1, within fifteen (15) days of Design-Builder’s receipt of Department’s Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Preliminary Schedule in accordance with Exhibit 11.1 (Special Provision for Design-Build Schedules). The Preliminary Schedule shall be the basis for monitoring the Design-Builder’s performance of the Work until such time as a Baseline Schedule has been approved by Department in accordance with Section 11.1.2 below. Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Preliminary Schedule.

Appears in 2 contracts

Samples: Lump Sum Design Build Agreement, Lump Sum Design Build Agreement

Preliminary Schedule. Unless otherwise stated in Exhibit 11 to Parts 3, 4 and 5, within fifteen (15) days of Design-Builder’s receipt of Department’s Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Preliminary Schedule in accordance with Exhibit 11.1 (Special Provision for Design-Build Schedules). The Preliminary Schedule shall be the basis for monitoring the Design-Builder’s performance of the Work until such time as a Baseline Schedule has been approved by Department in accordance with Section 11.1.2 below. Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Preliminary Schedule.

Appears in 2 contracts

Samples: Project Specific Terms Agreement, Project Specific Terms Agreement

AutoNDA by SimpleDocs

Preliminary Schedule. Unless otherwise stated in Exhibit 1, within Within fifteen (15) days of Design-Builder’s receipt of Department’s the Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Preliminary Schedule in accordance with Exhibit 11.1 (Special Provision for Design-Build Schedules)17. The Preliminary Schedule shall be the basis for monitoring the Design-Builder’s performance of the Work until such time as a Baseline Schedule has been approved by Department in accordance with Section 11.1.2 below. Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Preliminary Schedule.

Appears in 1 contract

Samples: Comprehensive Agreement