Preliminary Schedule. Within fifteen (15) days of Design-Builder’s receipt of LNTP1, Design-Builder shall submit to Department, for its review and approval, a Preliminary Schedule in accordance with Section 2.3 of the Technical Requirements. The Preliminary Schedule shall be the basis for monitoring Design-Builder’s performance of the Work (including the Early Work) until such time as a Baseline Schedule has been approved by Department in accordance with Section 11.1.2 below. Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Early Work Payment until such time Design-Builder furnishes an approved Preliminary Schedule.
Appears in 4 contracts
Samples: Comprehensive Agreement, Comprehensive Agreement, Comprehensive Agreement