Common use of Price Increase Clause in Contracts

Price Increase. When the ratio SI/ SB is calculated to be greater than 1.05, the Contractor will receive a price increase, for applicable steel material having an invoice date that falls within the month for which the SI index price was posted, to be determined in accordance with the following formula:

Appears in 8 contracts

Samples: Highway Construction Contract, Highway Construction Contract, Highway Construction Contract

AutoNDA by SimpleDocs

Price Increase. When the ratio SI/ SI/SB is calculated to be greater than 1.05, the Contractor will receive a price increase, for applicable steel material having an invoice date that falls within the month for which the SI index price was posted, to be determined in accordance with the following formula:

Appears in 1 contract

Samples: Construction Contract