Price Increase. When the ratio SI/ SB is calculated to be greater than 1.05, the Contractor will receive a price increase, for applicable steel material having an invoice date that falls within the month for which the SI index price was posted, to be determined in accordance with the following formula:
Appears in 8 contracts
Samples: Highway Construction Contract, Highway Construction Contract, Highway Construction Contract
Price Increase. When the ratio SI/ SI/SB is calculated to be greater than 1.05, the Contractor will receive a price increase, for applicable steel material having an invoice date that falls within the month for which the SI index price was posted, to be determined in accordance with the following formula:
Appears in 1 contract
Samples: Construction Contract