Common use of Quality control system Clause in Contracts

Quality control system. 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP"). 11.2.2 The Contractor shall, within 4(four) weeks of the letter of Award, submit to the Employer's Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing and calibration in accordance with the Specifications and Standards and Good Industry Practice; and (c) internal quality audit system. The Employer's Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan. 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 2 contracts

Samples: Epc Agreement, Epc Agreement

AutoNDA by SimpleDocs

Quality control system. 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP"). 11.2.2 The Contractor shall, within 4(four30 (thirty) weeks days of the letter of AwardAppointed Date, submit to the Employer's Authority’s Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing and calibration in accordance with the Specifications and Standards and Good Industry Practice; and (c) internal quality audit system. . 11.2.3 The Employer's Authority’s Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 11.2.4 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets Works, Materials and workmanship in accordance with the Quality Assurance Plan. 11.2.4 11.2.5 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

Quality control system. 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP"). 11.2.2 The Contractor shall, within 4(four) weeks of the letter of Award, submit to the Employer's Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing and calibration in accordance with the Specifications and Standards and Good Industry Practice; and (c) internal quality audit system. The Employer's Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan. 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement

Quality control system. 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP"). 11.2.2 The Contractor shall, within 4(four30 (thirty) weeks days of the letter of AwardAppointed Date, submit to the Employer's ’s Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site Site activities, and proforma for testing and calibration in accordance with the Standard and Specifications and Standards and Good Industry Practice; and (c) internal quality audit system. The Employer's ’s Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan. 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 1 contract

Samples: Demonstration Agreement

Quality control system. 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP"). 11.2.2 The Contractor shall, within 4(four30 (thirty) weeks days of the letter of AwardAppointed Date, submit to the Employer's Employer‟s Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site Site activities, and proforma for testing and calibration in accordance with the Standard and Specifications and Standards and Good Industry Practice; and (c) internal quality audit system. The Employer's Employer‟s Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan. 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 1 contract

Samples: Epc Agreement

AutoNDA by SimpleDocs

Quality control system. 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP")”) in accordance with ISO-9001. 11.2.2 The Contractor shall, within 4(four30 (thirty) weeks days of the letter of AwardAppointed Date, submit to the Employer's Authority’s Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing and calibration in accordance with the Specifications and Standards and Good Industry Practice; and (c) internal quality audit system. The Employer's Authority’s Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets Assets, Materials and workmanship in accordance with the Quality Assurance Plan. 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 1 contract

Samples: Engineering, Procurement and Construction (Epc) Agreement

Quality control system. 11.2.1 (i) The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP"). 11.2.2 (ii) The Contractor shall, within 4(four30 (thirty) weeks days of the letter of AwardAppointed Date, submit to the Employer's Engineer its Quality Assurance Plan which shall include the following:the (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing and calibration in accordance with the Specifications for Road and Standards Bridge Works issued by MORTH, relevant IRC specifications and Good Industry Practice; and (c) internal quality audit system. The Employer's Authority’s Engineer shall convey its comments approval to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 (iii) The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan. 11.2.4 (iv) The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Contract

Quality control system. 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the "Quality Assurance Plan" or "QAP"). 11.2.2 The Contractor shall, within 4(four30 (thirty) weeks days of the letter of AwardAppointed Date, submit to the Employer's ’s Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site Site activities, and proforma for testing and calibration in accordance with the Standard and Specifications and Standards and Good Industry Practice; and (c) internal quality audit system. The Employer's ’s Engineer shall convey its comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan. 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.

Appears in 1 contract

Samples: Contract Agreement for Design and Construction

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!