Quality control system. (i) The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the “Quality Assurance Plan” or “QAP”). (ii) The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the Authority’s Engineer its Quality Assurance Plan which shall include the following: (a) organisation, duties and responsibilities, procedures, inspections and documentation; (b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma for testing and calibration in accordance with the Specifications for Automated Multilevel Parking, Firefighting, Works issued by MORTH,NBCC, relevant IRC specifications, IS code and Good Industry Practice; and (c) internal quality audit system. The Authority’s Engineer shall convey its approval to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2. (iii) The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan. (iv) The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Quality control system. (i) 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the “Quality Assurance Plan” or “QAP”).
(ii) 11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit submits to the Authority’s AUTHORITY’S/GMDAs Engineer its Quality Assurance Plan which shall include the following:
(a) organisationorganization, duties and responsibilities, procedures, inspections and documentation;
(b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site activities, and proforma Performa for testing and calibration in accordance with the Specifications for Automated Multilevel Parking, Firefighting, Road and Bridge Works issued by MORTH,NBCC, relevant IRC specifications, IS code specifications and Good Industry Practice; and
(c) internal Internal quality audit system. The Authority’s AUTHORITY’S/GMDAs Engineer shall convey its approval comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
(iii) 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labourlabor, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan.
(iv) 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 1 contract
Quality control system. (i) 11.2.1 The Contractor shall establish a quality control mechanism to ensure compliance with the provisions of this Agreement (the “Quality Assurance Plan” or “QAP”).
(ii) 11.2.2 The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to the AuthorityEmployer’s Engineer its Quality Assurance Plan which shall include the following:
(a) organisation, duties and responsibilities, procedures, inspections and documentationDocumentation;
(b) quality control mechanism including sampling and testing of Materials, test frequencies, standards, acceptance criteria, testing facilities, reporting, recording and interpretation of test results, approvals, check list for site Site activities, and proforma for testing and calibration in accordance with the Specifications for Automated Multilevel Parking, Firefighting, Road and Bridge Works issued by MORTH,NBCC, relevant IRC specifications, IS code BIS standards, international Standards relevant to project components and Good Industry Practice; and
(c) internal Internal quality audit system. The AuthorityEmployer’s Engineer shall convey its approval comments to the Contractor within a period of 21 (twenty-one) days of receipt of the QAP stating the modifications, if any, required, and the Contractor shall incorporate those in the QAP to the extent required for conforming with the provisions of this Clause 11.2.
(iii) 11.2.3 The Contractor shall procure all documents, apparatus and instruments, fuel, consumables, water, electricity, labour, Materials, samples, and qualified personnel as are necessary for examining and testing the Project Assets and workmanship in accordance with the Quality Assurance Plan.
(iv) 11.2.4 The cost of testing of Construction, Materials and workmanship under this Article 11 shall be borne by the Contractor.
Appears in 1 contract
Samples: Epc Contract