Reconciliation of Unit Price Items Sample Clauses

Reconciliation of Unit Price Items. 7.12.4.1 The Contracting Authority may increase, decrease, or delete entirely the scheduled quantities of Work to be performed and materials to be furnished by Change Order. 7.12.4.2 The A/E shall issue a Change Order to reconcile the difference between the scheduled and actual quantities of Work performed and materials furnished. 7.12.4.3 If the actual quantity of a Unit Price item differs from the scheduled quantity by 20 percent or more, so that application of the Unit Price to the quantities of Work proposed would create an undue hardship on either the Owner or the Contractor, the A/E shall issue a Proposal Request and subsequent Change Order to adjust the Unit Price. .1 If a Unit Price is adjusted as described under Section 7.12.4.3, the new Unit Price will only apply to the units of Work performed that are (1) less than the 20 percent threshold if the Unit Price is changed on account of an over-estimation of the scheduled quantity of a Unit Price item involved in the Work or (2) in excess of the 20 percent threshold if the Unit Price is changed on account of an under-estimation of the scheduled quantity of a Unit Price item involved in the Work. 7.12.4.4 If the actual quantity of a Unit Price item exceeds the scheduled quantity by 20 percent or more, the Contractor shall immediately notify the A/E, who shall issue a Change Directive and subsequent Change Order to authorize an adjustment in the scheduled quantity.
AutoNDA by SimpleDocs
Reconciliation of Unit Price Items. 7.1.6.1 The Contracting Authority may increase, decrease, or delete entirely the scheduled quantities of Work to be performed and materials to be furnished by Change Order. 7.1.6.2 The parties shall enter into a Change Order to reconcile the difference between the scheduled and actual quantities of Work performed and materials furnished. 7.1.6.3 If the actual quantity of a Unit Price item exceeds the scheduled quantity by 20 percent or more, the DB shall immediately notify the Contracting Authority. If the actual quantity of a Unit Price item differs from the scheduled quantity by 20 percent or more, so that application of the Unit Price to the quantities of Work proposed would create an undue hardship on either the Owner or DB, the Contracting Authority shall issue a Proposal Request or the DB shall issue a request for a Change Order (as appropriate). The parties shall thereafter negotiate an appropriate adjustment of the Unit Price and scheduled quantity and enter into an associated Change Order. .1 If a Unit Price is adjusted as described under Section 7.1.6.3, the new Unit Price will only apply to the units of Work performed that are (1) less than the 20 percent threshold if the Unit Price is changed on account of an over-estimation of the scheduled quantity of a Unit Price item involved in the Work or (2) in excess of the 20 percent threshold if the Unit Price is changed on account of an under-estimation of the scheduled quantity of a Unit Price item involved in the Work.
Reconciliation of Unit Price Items. 7.12.4.1 The Contracting Authority may increase, decrease, or delete entirely the scheduled quantities of Work to be performed and materials to be furnished by Change Order. 7.12.4.2 The A/E shall issue a Change Order to reconcile the difference between the scheduled and actual quantities of Work performed and materials furnished. 7.12.4.3 If the actual quantity of a Unit Price item differs from the scheduled quantity by 20 percent or more, so that application of the Unit Price to the quantities of Work proposed would create an undue hardship on either the Owner or the Contractor, the A/E shall issue a Proposal Request and subsequent Change Order to adjust the Unit Price. 7.12.4.4 If the actual quantity of a Unit Price item exceeds the scheduled quantity by 20 percent or more, the Contractor shall immediately notify the A/E, who shall issue a Change Directive and subsequent Change Order to authorize an adjustment in the scheduled quantity.
Reconciliation of Unit Price Items. 8.12.4. 18.11.4.1 The Contracting Authority may increase, decrease, or delete entirely the scheduled quantities of Work to be performed and materials to be furnished by Change Order.
Reconciliation of Unit Price Items. Version Control Document 7.1.6.17.1.5.1 The Contracting Authority may increase, decrease, or delete entirely the scheduled quantities of Work to be performed and materials to be furnished by Change Order. 7.1.6.27.1.5.2 The A/E shall issue a Change Order to reconcile the difference between the scheduled and actual quantities of Work performed and materials furnished. 7.1.6.37.1.5.3 If the actual quantity of a Unit Price item differs from the scheduled quantity by 20 percent or more, so that application of the Unit Price to the quantities of Work proposed would create an undue hardship on either the Owner or the Contractor, the A/E shall issue a Proposal Request and subsequent Change Order to adjust the Unit Price. .1 If a Unit Price is adjusted as described under Section 7.1.5.3, the new Unit Price will only apply to the units of Work performed that are (1) less than the 20 percent threshold if the Unit Price is changed on account of an over-estimation of the scheduled quantity of a Unit Price item involved in the Work or (2) in excess of the 20 percent threshold if the Unit Price is changed on account of an under-estimation of the scheduled quantity of a Unit Price item involved in the Work. 7.1.6.47.1.5.4 If the actual quantity of a Unit Price item exceeds the scheduled quantity by 20 percent or more, the Contractor shall immediately notify the A/E, who shall issue a Change Directive and subsequent Change Order to authorize an adjustment in the scheduled quantity.
Reconciliation of Unit Price Items. 7.12.4.1 The Contracting Authority may increase, decrease, or delete entirely the scheduled quantities of Work to be performed and materials to be furnished by Change Order. 7.12.4.2 The A/E shall assist the CM issue a Change Order to reconcile the difference between scheduled and actual quantities of Work performed and materials furnished. 7.12.4.3 If the actual quantity of a Unit Price item differs from the scheduled quantity by 20 percent or more, so that application of the Unit Price to the quantities of Work proposed would create an undue hardship on either the Owner or the Contractor, the A/E shall assist the CM issue a Proposal Request and subsequent Change Order to adjust the Unit Price. 7.12.4.4 If the actual quantity of a Unit Price item exceeds the scheduled quantity by 20 percent or more, the Contractor shall immediately notify the CM, who shall issue a Change Directive and subsequent Change Order to authorize an adjustment in the scheduled quantity, with assistance of the A/E.

Related to Reconciliation of Unit Price Items

  • Estimates and Reconciliation of Estimates Where estimated expenditures are used to determine the amount of the drawdown, the State will indicate in the terms of the State unique funding technique how the estimated amount is determined and when and how the State will reconcile the difference between the estimate and the State's actual expenditures.

  • Annual Reconciliation At the end of each calendar year or as soon thereafter as practicable Landlord shall deliver to Tenant a statement (“Annual Reconciliation”) of (a) the actual annual Operating Expenses and Tenant’s Percentage of Operating Expenses for the preceding year, and (b) the actual annual Real Property Taxes and Tenant’s Percentage of Real Property Taxes for the preceding year. If for any year, the sum of Tenant’s Percentage of Operating Expenses and Tenant’s Percentage of Real Property Taxes (as specified in the Annual Reconciliation) is less than the total amount of the estimated payments made by Tenant under Section 6.3.1 above for such year, then any such overpayment, or overpayments, shall be credited toward the monthly Rent next falling due after determination by Landlord of such overpayment or overpayments and shall be paid to Tenant in a lump sum for periods after the expiration of the Term. Similarly, if for any year, the sum of Tenant’s Percentage of Operating Expenses and Tenant’s Percentage of Real Property Taxes (as specified in the Annual Reconciliation) is more than the total amount of the estimated payments made by Tenant under Section 6.3.1 above for such year, then any such underpayment, or underpayments, shall be paid by Tenant to Landlord concurrently with the next regular monthly Basic Rent payment coming due after Tenant’s receipt of the Annual Reconciliation (or if the Term shall have expired or terminated, within thirty (30) days following Tenant’s receipt of such Annual Reconciliation).