Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Appears in 18 contracts
Samples: Construction Management Services Agreement, Construction Management Contract, Construction Management Contract
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction ContractorManager’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Appears in 6 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s Project' s actual plan or method of operation, or a contractual milestone date is more than fifteen thirty (1530) days behind, the Owner may require that a recovery schedule for completion of the remaining Work Contract work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of the Owner’s ' s request. The Recovery Schedule shall describe in detail the Construction Contractor’s Manager' s plan to complete the remaining Work Contract work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Initial Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone datesdate.
Appears in 5 contracts
Samples: Construction Management Contract, Construction Management Contract, Construction Management Contract
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, the Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of the Owner’s request. The Recovery Schedule shall describe in detail the Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Appears in 3 contracts
Samples: Project Construction Management Contract, Project Construction Management Contract, Project Construction Management Contract
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction ContractorManager’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Appears in 1 contract
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen three (153) days behind, Owner the Owner’s Project Representative may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven three (73) calendar days of the Owner’s Project Representative’s request. The Recovery Schedule shall describe in detail the Construction ContractorManager’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Appears in 1 contract
Samples: Construction Management Agreement
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the applicable Contract milestone dates.
Appears in 1 contract
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, the Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of the Owner’s request. The Recovery Schedule shall describe in detail Construction Contractorthe Design Builder’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Appears in 1 contract
Samples: Design Build Services Agreement
Recovery Schedule. If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, the Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of the Owner’s request. The Recovery Schedule shall describe in detail the Construction ContractorManager’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Appears in 1 contract
Samples: Construction Management Agreement