Recovery Schedule. 4.5.1 If at any time, the Work on any Critical Path item is delayed for a period 4.5.2 TxDOT shall notify DB Contractor within 14 days after receipt of each such 4.5.3 All costs incurred by DB Contractor in preparing, implementing and 4.5.4 If a TxDOT approved Recovery Schedule is not in place within 30 days
Appears in 7 contracts
Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement
Recovery Schedule. 4.5.1 If at any time, the Work on any Critical Path item is delayed for a period
4.5.2 TxDOT shall notify DB Contractor within 14 days after receipt of each such
4.5.3 All costs incurred by DB Contractor in preparing, implementing and
4.5.4 If a TxDOT approved DB Contractor fails to provide an acceptable Recovery Schedule is not in place within 30 daysas