Return/ release of Contract Performance Guarantee Sample Clauses

Return/ release of Contract Performance Guarantee. 3.6.1 The Procurer shall return/ release the Contract Performance Guarantee to the Seller at the end of three months after the completion of Term of this Agreement or extension thereof, unless the same is not invoked by the Procurer;
AutoNDA by SimpleDocs

Related to Return/ release of Contract Performance Guarantee

  • Performance Guarantee 9.4.1 The Concessionaire shall, for the performance of its obligations hereunder during the Concession Period, provide to the Authority no later than [90] days prior to expiry of the Performance Security, an irrevocable and unconditional guarantee from a Bank for a sum equivalent to Rs. ***** crore (Rupees ***** crore)7 in the form set forth in Schedule-FF (the “Performance Guarantee”). Until such time the Performance Guarantee is provided by the Concessionaire pursuant hereto and the same comes into effect, notwithstanding anything contained in clause 9.3 the Performance Security shall remain in force and effect, and upon such provision of the Performance Guarantee pursuant hereto, the Authority shall release the Performance Security to the Concessionaire.

  • Release of Performance Security (i) The Authority shall return the Performance Security to the Contractor within 60 (sixty) days of the expiry of the Maintenance Period or the Defects Liability Period, whichever is later, under this Agreement. Notwithstanding the aforesaid, the Parties agree that the Authority shall not be obliged to release the Performance Security until all Defects identified during the Defects Liability Period have been rectified.

  • Continuing Contract Performance Pending final resolution of a Claim including litigation, unless otherwise agreed in writing the Contractor shall proceed diligently with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract Documents.

  • Lodgement of SWS wage assessment agreement C.6.1 All SWS wage assessment agreements under the conditions of this schedule, including the appropriate percentage of the relevant minimum wage to be paid to the employee, must be lodged by the employer with Fair Work Australia.

  • Return of Performance Bank Guarantee Payment on Order Instrument

  • Amendment of Release Schedule The new release schedule will apply 10 days after the Escrow Agent receives a certificate signed by a director or officer of the Issuer authorized to sign

  • F2 Monitoring of Contract Performance F2.1 The Contractor shall immediately inform the Authority if any aspect of the Contract is not being or is unable to be performed, the reasons for non-performance, any corrective action and the date by which that action will be completed.

  • OUTCOME IF GRANTEE CANNOT COMPLETE REQUIRED PERFORMANCE Unless otherwise specified in this Statement of Work, if Grantee cannot complete or otherwise comply with a requirement included in this Statement of Work, HHSC, at its sole discretion, may impose remedies or sanctions outlined under Contract Attachment C, Local Mental Health Authority Special Conditions, Section 7.09 (Remedies and Sanctions).

  • Monitoring of Contract Performance The Contractor shall comply with the monitoring arrangements set out in the Monitoring Schedule including, but not limited to, providing such data and information as the Contractor may be required to produce under the Contract.

  • Excuse for Nonperformance or Delayed Performance Except with respect to defaults of subcontractors, Contractor/Vendor shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure by Contractor/Vendor to make progress in the prosecution of the work hereunder which endangers such performance) if Contractor/Vendor has notified the Commission or designee within 15 days after the cause of the delay and the failure arises out of causes such as: acts of God; acts of the public enemy; acts of the State and any other governmental entity in its sovereign or contractual capacity; fires; floods; epidemics; quarantine restrictions; strikes or other labor disputes; freight embargoes; or unusually severe weather. If the failure to perform is caused by the failure of a subcontractor to perform or to make progress, and if such failure arises out of causes similar to those set forth above, Contractor/Vendor shall not be deemed to be in default, unless the services to be furnished by the subcontractor were reasonably obtainable from other sources in sufficient time to permit Contractor to meet the contract requirements. Upon request of Contractor, the Commission or designee shall ascertain the facts and extent of such failure, and, if such officer determines that any failure to perform was occasioned by any one or more of the excusable causes, and that, but for the excusable cause, Contractor’s progress and performance would have met the terms of the contract, the delivery schedule shall be revised accordingly, subject to the rights of the State under the clause entitled (in fixed-price contracts, “Termination for Convenience,” in cost-reimbursement contracts, “Termination”). (As used in this Paragraph of this clause, the term “subcontractor” means subcontractor at any tier).