Schedule for Achieving Substantial Completion Sample Clauses

Schedule for Achieving Substantial Completion. The Design-Build Firm shall achieve Substantial Completion by the applicable Scheduled Date of Substantial Completion to be established for NEOC and NESC, as shown in the Project Schedule (Exhibit 6). In the event of Excusable Delay, the Scheduled Date of Substantial Completion shall be adjusted by adding the resulting aggregate number of days of Excusable Delay. In such event, Delay Liquidated Damages shall accrue from the Scheduled Date of Substantial Completion, as the same may be extended. Owner may deduct and offset from and against any amounts due Design-Build Firm a sum equal to the amount of any Delay Liquidated Damages due Owner through the date that Final Completion is achieved.
AutoNDA by SimpleDocs
Schedule for Achieving Substantial Completion. Notwithstanding the Company’s achievement of Substantial Completion for agreed upon portions or components of the Wastewater Facilities, the Company shall achieve Substantial Completion of all Wastewater Facilities and the entire system by the Substantial Completion Date. In the event of one or more delays in the Design/Build Work caused by an Uncontrollable Circumstance occurring during the Design/Build Period, the scheduled Substantial Completion Date shall be the date determined by adding to the Substantial Completion Date the aggregate number of days of delay in the performance of the Design/Build Work caused by such Uncontrollable Circumstance and approved in a Change Order, subject to the requirements and limitations set forth in Section 6.8 of this Agreement. In the event of any such adjustment, delay liquidated damages payable by the Company under this Section, if any, shall be payable from the adjusted Substantial Completion Date.

Related to Schedule for Achieving Substantial Completion

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • After Substantial Completion § 12.2.2.1 In addition to the Contractor’s obligations under Section 3.5, if, within one year after the date of Substantial Completion of the Work or designated portion thereof or after the date for commencement of warranties established under Section 9.9.1, or by terms of any applicable special warranty required by the Contract Documents, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of notice from the Owner to do so, unless the Owner has previously given the Contractor a written acceptance of such condition. The Owner shall give such notice promptly after discovery of the condition. During the one-year period for correction of Work, if the Owner fails to notify the Contractor and give the Contractor an opportunity to make the correction, the Owner waives the rights to require correction by the Contractor and to make a claim for breach of warranty. If the Contractor fails to correct nonconforming Work within a reasonable time during that period after receipt of notice from the Owner or Architect, the Owner may correct it in accordance with Section 2.5.

  • At Substantial Completion and Final Completion the Contractor shall provide a certification letter certifying that the Work does not contain asbestos as required by the UTUGCs.

  • TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to run.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ « » ] The date of this Agreement. [ « » ] A date set forth in a notice to proceed issued by the Owner. [ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) « » If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by September 30, 2022.

  • Status Substantial Compliance Analysis The Compliance Officer found that PPB is in substantial compliance with Paragraph 80. See Sections IV and VII Report, p. 17. COCL carefully outlines the steps PPB has taken—and we, too, have observed—to do so. Id. We agree with the Compliance Officer’s assessment. In 2018, the Training Division provided an extensive, separate analysis of data concerning ECIT training. See Evaluation Report: 2018 Enhanced Crisis Intervention Training, Training usefulness, on-the-job applications, and reinforcing training objectives, February 2019. The Training Division assessed survey data showing broad officer support for the 2018 ECIT training. The survey data also showed a dramatic increase in the proportion of officers who strongly agree that their supervisors are very supportive of the ECIT program, reaching 64.3% in 2018, compared to only 14.3% in 2015: The Training Division analyzed the survey results of the police vehicle operator training and supervisory in-service training, as well. These analyses were helpful in understanding attendees’ impressions of training and its application to their jobs, though the analyses did not reach as far as the ECIT’s analysis of post-training on- the-job assessment. In all three training analyses, Training Division applied a feedback model to shape future training. This feedback loop was the intended purpose of Paragraph 80. PPB’s utilization of feedback shows PPB’s internalization of the remedy. We reviewed surveys of Advanced Academy attendees, as well. Attendees were overwhelmingly positive in response to the content of most classes. Though most respondents agreed on the positive aspects of keeping the selected course in the curriculum, a handful of attendees chose options like “redundant” and “slightly disagree,” indicating that the survey tools could be used for critical assessment and not merely PPB self-validation. We directly observed PPB training and evaluations since our last report. PPB provided training materials to the Compliance Officer and DOJ in advance of training. Where either identified issues, PPB worked through those issues and honed its materials. As Paragraph 80 requires, PPB’s training included competency-based evaluations, namely: knowledge checks (i.e., quizzes on directives), in-class responsive quizzes (using clickers to respond to questions presented to the group); knowledge tests (examinations via links PPB sent to each student’s Bureau-issued iPhone); demonstrated skills and oral examination (officers had to show proficiency in first aid skills, weapons use, and defensive tactics); and scenario evaluations (officers had to explain their reasoning for choices after acting through scenarios). These were the same sort of competency-based evaluations we commended in our last report. In this monitoring period, PPB applied the same type of evaluations to supervisory-level training as well as in-service training for all sworn members. PPB successfully has used the surveys, testing, and the training audit.

Time is Money Join Law Insider Premium to draft better contracts faster.