Schedule Revisions. 6 If the sequence of construction differs significantly, as determined by the District’s Representative, from the 7 Construction Schedule, the Entity shall submit within fifteen (15) days a revised schedule to the District’s 8 Representative for acceptance. Updating the Construction Schedule to reflect actual progress shall not be 9 considered revisions to the Construction Schedule. 10 11 When a Proposed Change Order is issued which has the potential to impact specified completion dates, a 12 Network Window shall be prepared by the Entity to reflect the impact of such changes as expeditiously as is 13 reasonably possible in light of the nature, quantity and timing of potential changes. The District’s 14 Representative will promptly review and act on the Network Window. If the Network Window has been 15 accepted by the Owner and the Entity permitted by the Owner to proceed with the Proposed Change Order, the 16 Network Window shall be incorporated into the Construction Schedule. Time extensions will be considered 17 only to the extent there is insufficient remaining float to accommodate these changes, and pursuant to Article 18 14 of these General Construction Terms and Conditions. No additional cost beyond that provided in Article 15 19 will be allowed for the incorporation of approved Proposed Change Orders into the Construction Schedule, 20 except that, if Owner Initiated Changes, as defined and described in Section 15.02, exceed twelve percent 21 (12%) of the Total Base Rent, the Entity shall be entitled to compensation for its added costs of updating and 22 maintaining the schedule as a result of such changes. Such added costs must be properly substantiated by 23 supporting data. 24 25 Should the Entity, after acceptance of the Construction Schedule, intend to change its plan of Construction, 26 it shall submit their requested revisions to the District’s Representative, along with a written statement of 27 the revision, including a description of the logic for rescheduling the Work, methods of maintaining 28 adherence to Intermediate milestones and other specific dates and the reasons for the revisions. If the 29 requested changes are acceptable to the District’s Representative, they will be incorporated into the 30 Construction Schedule in the next reporting period. 31 32 Schedule revisions shall be submitted at least seven (7) days prior to the date of submission of update 33 information. The Owner will have seven (7) days to review the revisions. 34
Appears in 3 contracts
Samples: Facilities Lease Agreement, Facilities Lease Agreement, Facilities Lease Agreement
Schedule Revisions. 6 8 If the sequence of construction differs significantly, as determined by the District’s Representative, 9 from the 7 Construction Schedule, the Entity shall submit within fifteen (15) days a revised schedule 10 to the District’s 8 Representative for acceptance. Updating the Construction Schedule to reflect 11 actual progress shall not be 9 considered revisions to the Construction Schedule. 10 11 13 When a Proposed Change Order is issued which has the potential to impact specified completion 14 dates, a 12 Network Window Fragnet shall be prepared by the Entity to reflect the impact of such changes as 15 expeditiously as is 13 reasonably possible in light of the nature, quantity and timing of potential 16 changes. The District’s 14 Representative will promptly review and act on the Network WindowFragnet. If the Network Window Fragnet 17 has been 15 accepted by the Owner and the Entity permitted by the Owner to proceed with the 18 Proposed Change Order, the 16 Network Window Fragnet shall be incorporated into the Construction Schedule. Time 19 extensions will be considered 17 only to the extent there is insufficient remaining float to accommodate 20 these changes, and pursuant to Article 18 14 of these General Construction Terms and Conditions. No 21 additional cost beyond that provided in Article 15 19 will be allowed for the incorporation of approved 22 Proposed Change Orders into the Construction Schedule, 20 except that, if Owner Initiated Changes, 23 as defined and described in Section 15.02, exceed twelve percent 21 (12%) of the Total Base Rent, the 24 Entity shall be entitled to compensation for its added costs of updating and 22 maintaining the schedule 25 as a result of such changes. Such added costs must be properly substantiated by 23 supporting data. 24 25 27 Should the Entity, after acceptance of the Construction Schedule, intend to change its plan of 28 Construction, 26 it shall submit their requested revisions to the District’s Representative, along with a 29 written statement of 27 the revision, including a description of the logic for rescheduling the Work, 30 methods of maintaining 28 adherence to Intermediate milestones and other specific dates and the reasons for the revisions. If the 29 requested changes are acceptable to the District’s Representative, 32 they will be incorporated into the 30 Construction Schedule in the next reporting period. 31 32 34 Schedule revisions shall be submitted at least seven (7) days prior to the date of submission of 35 update 33 information. The Owner will have seven (7) days to review the revisions. 34.
Appears in 1 contract
Samples: Facilities Lease Agreement
Schedule Revisions. 6 If the sequence of construction differs significantly, as determined by the District’s Representative, from the 7 Construction Schedule, the Entity shall submit within fifteen (15) days a revised schedule to the District’s 8 Representative for acceptance. Updating the Construction Schedule to reflect actual progress shall not be 9 considered revisions to the Construction Schedule. 10 11 When a Proposed Change Order is issued which has the potential to impact specified completion dates, a 12 Network Window Fragnet shall be prepared by the Entity to reflect the impact of such changes as expeditiously as is reasonably 13 reasonably possible in light of the nature, quantity and timing of potential changes. The District’s 14 Representative will 14 promptly review and act on the Network WindowFragnet. If the Network Window Fragnet has been 15 accepted by the Owner and the Entity 15 permitted by the Owner to proceed with the Proposed Change Order, the 16 Network Window Fragnet shall be incorporated into the 16 Construction Schedule. Time extensions will be considered 17 only to the extent there is insufficient remaining 17 float to accommodate these changes, and pursuant to Article 18 14 of these General Construction Terms and 18 Conditions. No additional cost beyond that provided in Article 15 19 will be allowed for the incorporation of 19 approved Proposed Change Orders into the Construction Schedule, 20 except that, if Owner Initiated Changes, as 20 defined and described in Section 15.02, exceed twelve percent 21 (12%) of the Total Base Rent, the Entity shall 21 be entitled to compensation for its added costs of updating and 22 maintaining the schedule as a result of such 22 changes. Such added costs must be properly substantiated by 23 supporting data. 23 24 25 Should the Entity, after acceptance of the Construction Schedule, intend to change its plan of Construction, 26 25 it shall submit their requested revisions to the District’s Representative, along with a written statement of 27 26 the revision, including a description of the logic for rescheduling the Work, methods of maintaining 28 27 adherence to Intermediate milestones and other specific dates and the reasons for the revisions. If the 29 28 requested changes are acceptable to the District’s Representative, they will be incorporated into the 30 29 Construction Schedule in the next reporting period. 30 31 32 Schedule revisions shall be submitted at least seven (7) days prior to the date of submission of update 33 32 information. The Owner will have seven (7) days to review the revisions. 3433
Appears in 1 contract
Samples: Facilities Lease Agreement
Schedule Revisions. 6 If the sequence of construction differs significantly, as determined by the District’s Representative, from the 7 Construction Schedule, the Entity shall submit within fifteen (15) days a revised schedule to the District’s 8 Representative for acceptance. Updating the Construction Schedule to reflect actual progress shall not be 9 considered revisions to the Construction Schedule. 10 11 When a Proposed Change Order is issued which has the potential to impact specified completion dates, a 12 Network Window shall be prepared by the Entity to reflect the impact of such changes as expeditiously as is 13 reasonably possible in light of the nature, quantity and timing of potential changes. The District’s Representative 14 Representative will promptly review and act on the Network Window. If the Network Window has been 15 accepted by the Owner 15 and the Entity permitted by the Owner to proceed with the Proposed Change Order, the 16 Network Window shall 16 be incorporated into the Construction Schedule. Time extensions will be considered 17 only to the extent there is 17 insufficient remaining float to accommodate these changes, and pursuant to Article 18 14 of these General 18 Construction Terms and Conditions. No additional cost beyond that provided in Article 15 19 will be allowed for 19 the incorporation of approved Proposed Change Orders into the Construction Schedule, 20 except that, if Owner 20 Initiated Changes, as defined and described in Section 15.02, exceed twelve percent 21 (12%) of the Total Base 21 Rent, the Entity shall be entitled to compensation for its added costs of updating and 22 maintaining the schedule 22 as a result of such changes. Such added costs must be properly substantiated by 23 supporting data. 23 24 25 Should the Entity, after acceptance of the Construction Schedule, intend to change its plan of Construction, 26 it 25 shall submit their requested revisions to the District’s Representative, along with a written statement of 27 the 26 revision, including a description of the logic for rescheduling the Work, methods of maintaining 28 adherence to 27 Intermediate milestones and other specific dates and the reasons for the revisions. If the 29 requested changes 28 are acceptable to the District’s Representative, they will be incorporated into the 30 Construction Schedule in the 29 next reporting period. 30 31 32 Schedule revisions shall be submitted at least seven (7) days prior to the date of submission of update 33 32 information. The Owner will have seven (7) days to review the revisions. 3433
Appears in 1 contract
Samples: Facilities Lease Agreement
Schedule Revisions. 6 If the sequence of construction differs significantly, as determined by the District’s Representative, from the 7 Construction Schedule, the Entity shall submit within fifteen (15) days a revised schedule to the District’s 8 Representative for acceptance. Updating the Construction Schedule to reflect actual progress shall not be 9 considered revisions to the Construction Schedule. 10 11 When a Proposed Change Order is issued which has the potential to impact specified completion dates, a 12 Network Window Fragnet shall be prepared by the Entity to reflect the impact of such changes as expeditiously as is reasonably 13 reasonably possible in light of the nature, quantity and timing of potential changes. The District’s 14 Representative will 14 promptly review and act on the Network WindowFragnet. If the Network Window Fragnet has been 15 accepted by the Owner and the Entity 15 permitted by the Owner to proceed with the Proposed Change Order, the 16 Network Window Fragnet shall be incorporated into the 16 Construction Schedule. Time extensions will be considered 17 only to the extent there is insufficient remaining 17 float to accommodate these changes, and pursuant to Article 18 14 of these General Construction Terms and 18 Conditions. No additional cost beyond that provided in Article 15 19 will be allowed for the incorporation of 19 approved Proposed Change Orders into the Construction Schedule, 20 except that, if Owner Initiated Changes, as 20 defined and described in Section 15.02, exceed twelve percent 21 (12%) of the Total Base Rent, the Entity shall 21 be entitled to compensation for its added costs of updating and 22 maintaining the schedule as a result of such 22 changes. Such added costs must be properly substantiated by 23 supporting data. 23 24 25 Should the Entity, after acceptance of the Construction Schedule, intend to change its plan of Construction, 26 25 it shall submit their requested revisions to the District’s Representative, along with a written statement of 27 26 the revision, including a description of the logic for rescheduling the Work, methods of maintaining 28 27 adherence to Intermediate milestones and other specific dates and the reasons for the revisions. If the 29 28 requested changes are acceptable to the District’s Representative, they will be incorporated into the 30 29 Construction Schedule in the next reporting period. 30 31 32 Schedule revisions shall be submitted at least seven (7) days prior to the date of submission of update 33 32 information. The Owner will have seven (7) days to review the revisions. 3433
Appears in 1 contract
Samples: Facilities Lease Agreement