Common use of Special/ temporary Right of Way Clause in Contracts

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Highway and the performance of its obligations under this Agreement.

Appears in 133 contracts

Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Construction Contract

AutoNDA by SimpleDocs

Special/ temporary Right of Way. β€Œ The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Highway and the performance of its obligations under this Agreement.

Appears in 29 contracts

Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction Agreement, Contract Agreement

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Highway and the performance of its obligations under this Agreement.

Appears in 14 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Railway Project Highway and the performance of its obligations under this Agreement.

Appears in 9 contracts

Samples: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction (Epc) Agreement

Special/ temporary Right of Way. The Contractor shall bear all costs and & charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Railway Project Highway and the performance of its obligations under this Agreement.

Appears in 4 contracts

Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Highway Foot track and the performance of its obligations under this Agreement.

Appears in 2 contracts

Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Highway Work and the performance of its obligations under this Agreement.

Appears in 2 contracts

Samples: General Conditions of Contract, General Conditions of Contract

AutoNDA by SimpleDocs

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Highway PROJECT and the performance of its obligations under this Agreement.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Pro- ject Highway and the performance of its obligations under this Agreement.

Appears in 1 contract

Samples: Construction Contract

Special/ temporary Right of Way. The Contractor shall bear all costs and charges for any special or temporary right of way required by it in connection with access to the Site. The Contractor shall obtain at its cost such facilities on or outside the Site as may be required by it for the purposes of the Project Highway and the performance of its obligations under this Agreement.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Agreement