Submittal Review. 7.10.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and Contractor. 7.10.2 The A/E shall also review drawings, calculations, and designs required of the Contractor and its Subcontractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which the Contract Documents expressly make the sole responsibility of the Contractor or one or more Subcontractors, Material Suppliers, or other persons). 7.10.3 The A/E shall act upon resubmission of corrected Submittals within 14 days of receiving them, or other period as mutually agreed by the A/E and Contractor. 7.10.4 The Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals. 7.10.5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor stating that its Submittal is being held, within 7 days of receiving it. 7.10.6 If the Project is administered using the State’s web-based project management software, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 5 contracts
Samples: Professional Services, Architect/Engineer Agreement, Architect/Engineer Agreement
Submittal Review. 7.10.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and submitting Contractor.
7.10.2 The A/E shall also review drawings, calculations, and designs required of the each Contractor and its Subcontractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which the Contract Documents expressly make the sole responsibility of the a Contractor or one or more Subcontractors, Material Suppliers, or other persons).
7.10.3 The A/E shall act upon resubmission of corrected Submittals within 14 days of receiving them, or other period as mutually agreed by the A/E and submitting Contractor.
7.10.4 The Each Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the a Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals.
7.10.5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The A/E shall issue a written notice to the submitting Contractor stating that its Submittal is being held, within 7 days of receiving it.
7.10.6 If the Project is administered using the State’s web-based project management software, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 3 contracts
Samples: Professional Services, Architect/Engineer Agreement, Architect/Engineer Agreement
Submittal Review. 7.10.1 8.9.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of after receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and Contractor.
7.10.2 8.9.2 The A/E shall also review drawings, calculations, and designs required of the Contractor and its Subcontractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which that the Contract Documents expressly make the sole responsibility of the Contractor or one or more Subcontractors, Material Suppliers, or other persons).
7.10.3 8.9.3 The A/E shall act upon resubmission of corrected Submittals within 14 days of after receiving them, or other another period as mutually agreed by the A/E and Contractor.
7.10.4 8.9.4 The Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals.
7.10.5 8.9.5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The Within seven days after receiving the Submittal, the A/E shall issue a written notice to the Contractor stating that its the Submittal is being held, within 7 days of receiving it.
7.10.6 8.9.6 If the Project is administered using the State’s web-based project management software, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 2 contracts
Samples: Architect/Engineer Agreement, Architect/Engineer Agreement
Submittal Review. 7.10.1 .1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and Contractor.the Contractor.
7.10.2 .2 The A/E shall also review drawings, calculations, and designs required of the Contractor and its Subcontractors Contractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which the Contract Documents expressly make the sole responsibility of the Contractor or one or more Contractors, Subcontractors, Material Suppliers, Suppliers or other persons).
7.10.3 .3 The A/E shall act upon resubmission of corrected Submittals within 14 days of receiving them, or other period as mutually agreed by the A/E and the Contractor.
7.10.4 The .4 A Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals.
7.10.5 .5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor stating that its Submittal is being held, within 7 days of receiving it.
7.10.6 If the Project is administered using the State’s web-based project management software, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 1 contract
Samples: Architect/Engineer Agreement
Submittal Review. 7.10.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and submitting Contractor.
7.10.2 The A/E shall also review drawings, calculations, and designs required of the Contractor and its Subcontractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which the Contract Documents expressly make the sole responsibility of the Contractor or one or more Contractors, Subcontractors, Material Suppliers, or other persons).
7.10.3 The A/E shall act upon resubmission of corrected Submittals within 14 days of receiving them, or other period as mutually agreed by the A/E and submitting Contractor.
7.10.4 The Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals.
7.10.5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor submitting Contractor, through the CM, stating that its the Submittal is being held, within 7 days of receiving it.
7.10.6 If the Project is administered using the State’s web-based project management software, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 1 contract
Samples: Professional Services
Submittal Review. 7.10.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and the Contractor.
7.10.2 The A/E shall also review drawings, calculations, and designs required of the Contractor and its Subcontractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which the Contract Documents expressly make the sole responsibility of the Contractor or one or more Subcontractors, Material Suppliers, or other persons).
7.10.3 The A/E shall act upon resubmission of corrected Submittals within 14 days of receiving them, or other period as mutually agreed by the A/E and the Contractor.
7.10.4 The Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals.
7.10.5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor stating that its Submittal is being held, within 7 days of receiving it.
7.10.6 If the Project is administered using the OAKS CIthe State’s web-based project management software, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 1 contract
Samples: Professional Services
Submittal Review. 7.10.1 8.10.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and Contractor.
7.10.2 8.10.2 The A/E shall also review drawings, calculations, and designs required of the Contractor and its Subcontractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which that the Contract Documents expressly make the sole responsibility of the Contractor or one or more Subcontractors, Material Suppliers, or other persons).
7.10.3 8.10.3 The A/E shall act upon resubmission of corrected Submittals within 14 days of receiving them, or other period as mutually agreed by the A/E and Contractor.
7.10.4 8.10.4 The Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals.
7.10.5 8.10.5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The A/E shall issue a written notice to the Contractor stating that its Submittal is being held, within 7 days of receiving it.
7.10.6 8.10.6 If the Project is administered using the State’s web-based project management software, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 1 contract
Samples: Professional Services
Submittal Review. 7.10.1 The A/E shall review Submittals such as Shop Drawings, Product Data, and Samples for conformity with design intent and conformity with the Contract Documents within 14 days of receiving Submittals or in accordance with the approved submittal schedule, or other period as mutually agreed by the A/E and a Contractor.
7.10.2 The A/E shall also review drawings, calculations, and designs required of the each Contractor and its Subcontractors and provided with such Submittals (except calculations and designs of manufacturers of original equipment and systems to be installed in the Project and except calculations and designs which the Contract Documents expressly make the sole responsibility of the a Contractor or one or more Subcontractors, Material Suppliers, or other persons).
7.10.3 The A/E shall act upon resubmission of corrected Submittals within 14 days of receiving them, or other period as mutually agreed by the A/E and a Contractor.
7.10.4 The Each Contractor shall review and stamp “approved” all Submittals before forwarding them to the A/E. If it is apparent to the A/E that the a Contractor has not reviewed the Submittals, or has conducted an incomplete review of them, the A/E may reject the Submittals.
7.10.5 The A/E may hold samples and other Submittals used to coordinate finishes, colors, patterns, textures, or other characteristics until Submittals for adjacent materials are available. The A/E shall issue a written notice to the submitting Contractor stating that its Submittal is being held, within 7 days of receiving it.
7.10.6 If the Project is administered using the State’s web-based project management softwareOAKS CI, the A/E shall receive and forward submittals to its Consultants, and return reviewed submittals to the Contractor, using the “Submittals” business process.
Appears in 1 contract