Common use of Summary Schedule Comparison Clause in Contracts

Summary Schedule Comparison. When requested by the ADR, Design-Builder shall, with its Interim Payment Applications, submit a graphical comparison of the Baseline CPM Schedule, the then-current Project Schedule, and an updated Progress and Completion Schedule (“the Summary Schedule Comparison”). The Summary Schedule Comparison shall condense key tasks, events, Work sequences, and Milestone Dates, vertically aligning a condensed graphical Baseline CPM Schedule, the then-current Project Schedule, and the updated Progress and Completion Schedule on one document, employing identically time-scaled grids.

Appears in 2 contracts

Samples: s3.us-east-2.amazonaws.com, s3.us-east-2.amazonaws.com

AutoNDA by SimpleDocs

Summary Schedule Comparison. When requested by the ADR, Design-Builder shall, with its Interim Payment Applications, submit a graphical comparison of the Baseline CPM Schedule, the then-current Project Schedule, and an updated Progress and Completion Schedule (“the Summary Schedule Comparison”). The Summary Schedule Comparison shall condense key tasks, events, Work sequences, and Milestone Dates, vertically aligning a condensed graphical Baseline CPM Schedule, the then-current Project Schedule, and the updated Progress and Completion Schedule on one document, employing identically time-scaled grids.

Appears in 1 contract

Samples: s3.us-east-2.amazonaws.com

Summary Schedule Comparison. When requested by the ADR, Design-Builder CM shall, with its Interim Payment Applications, submit a graphical comparison of the Baseline CPM Schedule, the then-then- current Project Schedule, and an updated Progress and Completion Schedule (“the Summary Schedule Comparison”). The Summary Schedule Comparison shall condense key tasks, events, Work sequences, and Milestone Dates, vertically aligning a condensed graphical Baseline CPM Schedule, the then-current Project Schedule, and the updated Progress and Completion Schedule on one document, employing identically time-scaled grids.

Appears in 1 contract

Samples: Form of Agreement

AutoNDA by SimpleDocs

Summary Schedule Comparison. When requested by the ADR, Design-Builder Contractor shall, with its Interim Payment Applications, submit a graphical comparison of the Baseline CPM Schedule, the then-then- current Project Schedule, and an updated Progress and Completion Schedule (“the Summary Schedule Comparison”). The Summary Schedule Comparison shall condense key tasks, events, Work sequences, and Milestone Dates, vertically aligning a condensed graphical Baseline CPM Schedule, the then-current Project Schedule, and the updated Progress and Completion Schedule on one document, employing identically time-scaled grids.

Appears in 1 contract

Samples: Form of Agreement