Testing Procedure and Protocols. (i) At least one hundred and twenty (120) Days before the scheduled commencement of the testing and Commissioning of the Facility, the Company shall submit to BPDB detailed procedures and protocols to be used during the corresponding testing. (ii) The Engineer and BPDB shall have the opportunity to provide written comments on the proposed procedure and protocols within thirty (30) Days of receipt from the Company of said documentation, and the three Parties will reach an agreement on the procedures and protocols to be used for testing not later than sixty (60) Days prior to the scheduled commencement of the respective testing and Commissioning; provided, that: (A) if BPDB fails to submit written comments to the Company within the thirty
Appears in 6 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement