The Change Order. The Change Order is the instrument by which adjustments in the Contract Sum and the Contract Time are effected. The Change Order shall be accompanied by a breakdown as set forth in Paragraph 3.
Appears in 71 contracts
Samples: Construction Contract, Design Build Contract, Design Build Contract
The Change Order. The Change Order is the instrument by which adjustments in the Contract Sum and the Contract Time are effected. The Change Order shall be accompanied by a breakdown as set forth in Paragraph 33.4.
Appears in 14 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
The Change Order. The Change Order is the instrument by which adjustments in the Contract Sum and the Contract Time are effected. The Change Order shall be accompanied by a breakdown as set forth in Paragraph 3.Paragraph
Appears in 3 contracts
Samples: Construction Management Agreement, Design Bid Build Construction Contract, Design Bid Build Construction Contract
The Change Order. The Change Order is the instrument by which adjustments in the Contract Sum and the Contract Time are effected. The Change Order shall be accompanied by a breakdown as set forth in Paragraph 33.2.
Appears in 3 contracts
Samples: Design Bid Build Construction Contract, Design Bid Build Construction Contract, Construction Contract
The Change Order. The Change Order is the instrument by which adjustments in the Contract Sum and the Contract Time are effectedaffected. The Change Order shall be accompanied by a breakdown as set forth in Paragraph 33.4.
Appears in 3 contracts
Samples: Construction Management at Risk Agreement, Construction Management at Risk Agreement, Construction Management at Risk Agreement
The Change Order. The Change Order is the instrument by which adjustments in the Contract Sum and the Contract Time are effected. The Change Order shall be accompanied by a cost breakdown as set forth in Paragraph 3.Section
Appears in 1 contract
Samples: Construction Management Agreement
The Change Order. The Change Order is the instrument by which adjustments in the Contract Sum and the Contract Time are effected. The Change Order shall be accompanied by a cost breakdown as set forth in Paragraph 3.
Appears in 1 contract
Samples: Construction Management Agreement