Trenching Requirements. Project in Excess of Twenty-Five Thousand Dollars ($25,000)
Trenching Requirements. Applicant is responsible for all trenching relative to the Gas Extension Installation covered in the Contract. Joint trench width shall be as specified in the Utility Gas Construction Standard 19.1. For gas trench only (GTO), the trench shall be wide enough to provide a minimum of 3-inches of sand padded clearance at side of the installed gas pipe. All trenching, joint or GTO shall be performed according to the following requirements:
Trenching Requirements a. If the contract involves digging trenches or other excavations that extend deeper than four feet below the surface, the Contractor shall: