Voltage Ride-Through Capability. An Asynchronous Generating Facility shall be able to remain online during voltage disturbances up to the time periods and associated voltage levels set forth in the requirements below.
Voltage Ride-Through Capability. Provide voltage ride-through time duration settings (per-unit voltage set point and corresponding ride-through time), reflecting the settings for the plant level controller. An example of a voltage ride-through time duration curve for applicable units is provided below for reference.
Voltage Ride-Through Capability. GBX project shall comply with following (please note, some of them states same set of requirements however for avoidance of doubt all possible references are included that are to be complied): • NERC PRC024-3 • FERC Order 661A