Water Service. 4.6.1 The Developer shall construct the water lines in and serving the Site Plan and pay the City for and to install all meters and make connection of Site Plan to City water system. 4.6.2 The Developer shall pay the cost of water main and accessories to serve the Site Plan from a point to be approved by the Planning Commission and the City Engineer. The Developer will also pay for the water mains and accessories within the Site Plan, including service lines, accessories from the main to the meter and all meters. 4.6.3 The Developer shall pay the cost of all engineering, inspection and laboratory cost relating to the water service system in or to the Site Plan, including but not limited to inspection and approval by the Tennessee Department of Public Health. The Developer shall provide the City with copies of comments and certificates from said Department. 4.6.4 If required by the City, the Developer shall install fire hydrants in accordance with the type service appropriate, the type and location as approved by the Planning Commission with recommendation from the City’s Fire Chief and the City Engineer. 4.6.5 Water Development fee, $1,500.00 per connection. 4.6.6 Water connection fee, per lot 1 or 2” meter is $500 plus the cost of the meter.
Appears in 1 contract
Water Service. 4.6.1 The Developer shall construct the water lines in and serving the Site Plan and pay the City for and to install all meters and make connection of Site Plan to City water system.
4.6.2 The Developer shall pay the cost of water main and accessories to serve the Site Plan from a point to be approved by the Planning Commission and the City Engineer. The Developer will also pay for the water mains and accessories within the Site Plan, including service lines, accessories from the main to the meter and all meters.
4.6.3 The Developer shall pay the cost of all engineering, inspection and laboratory cost relating to the water service system in or to the Site Plan, including but not limited to inspection and approval by the Tennessee Department of Public Health. The Developer shall provide the City with copies of comments and certificates from said Department.
4.6.4 If required by the City, the Developer shall install fire hydrants in accordance with the type service appropriate, the type and location as approved by the Planning Commission with recommendation from the City’s Fire Chief and the City Engineer.
4.6.5 Water Development fee, $1,500.00 200.00 per connection.
4.6.6 Water connection fee, per lot 1 or 2” meter is $500 plus the cost of the meter. .
Appears in 1 contract
Water Service. 4.6.1 The Developer shall construct the water lines in and serving the Site Plan and pay the City for and to install all meters and make connection of Site Plan to City water system.
4.6.2 The Developer shall pay the cost of water main and accessories to serve the Site Plan from a point to be approved by the Planning Commission and the City Engineer. The Developer will also pay for the water mains and accessories within the Site Plan, including service lines, accessories from the main to the meter and all meters.
4.6.3 The Developer shall pay the cost of all engineering, inspection and laboratory cost relating to the water service system in or to the Site Plan, including but not limited to inspection and approval by the Tennessee Department of Public Health. The Developer shall provide the City with copies of comments and certificates from said Department.
4.6.4 If required by the City, the Developer shall install fire hydrants in accordance with the type service appropriate, the type and location as approved by the Planning Commission with recommendation from the City’s Fire Chief and the City Engineer.
4.6.5 Water Development fee, $1,500.00 per connection.
4.6.6 Water connection fee, per lot 1 or 2” meter is $500 plus the cost of the meter. . All connections made to the water line or any lateral lines of the North Fork Creek water line shall be subject to a water development charge of the greater of $3,000 per acre or $1,200 per connection.
Appears in 1 contract
Water Service. 4.6.1 The Developer shall construct the water lines in and serving the Site Plan and pay the City for and to install all meters and make connection of Site Plan to City water system.
4.6.2 The Developer shall pay the cost of water main and accessories to serve the Site Plan from a point to be approved by the Planning Commission and the City Engineer. The Developer will also pay for the water mains and accessories within the Site Plan, including service lines, accessories from the main to the meter and all meters.
4.6.3 The Developer shall pay the cost of all engineering, inspection and laboratory cost relating to the water service system in or to the Site Plan, including but not limited to inspection and approval by the Tennessee Department of Public Health. The Developer shall provide the City with copies of comments and certificates from said Department.
4.6.4 If required by the City, the Developer shall install fire hydrants in accordance with the type service appropriate, the type and location as approved by the Planning Commission with recommendation from the City’s Fire Chief and the City Engineer.
4.6.5 Water Development development fee, $1,500.00 200.00 per connectionlot or dwelling unit.
4.6.6 Water connection fee, per lot 1 or 2” meter is $500 500.00 plus the cost of the meter.
Appears in 1 contract