Common use of Work Programmes Clause in Contracts

Work Programmes. a. The Concessionaire shall prepare in consultation with the Independent Engineer and submit a Project Implementation Schedule to the Authority before the Compliance Date. The programme shall include the following: i) The order in which the Concessionaire proposes to carry out the Works, internal and external services (including each stage of design, procurement, manufacture, delivery to Project Site, construction, erection, testing and commissioning). ii) All major events and activities in the production of Construction Documents. iii) The particulars for the pre‐construction reviews and for any other submissions, approvals and consents specified in this Concession Agreement. b. Any alternation/ revision by the Concessionaire in the Project Implementation Schedule shall be made in accordance with Article 12.5. c. If the progress of the Works does not conform to the Project Implementation Schedule, the Independent Engineer may instruct the Concessionaire to revise the Project Implementation Schedule, showing the modifications necessary to achieve completion as per Project Implementation Schedule. The Independent Engineer shall record the reasons for such revision of Project Implementation Schedule. d. The Concessionaire shall, whenever required by the Authority, provide in writing, for information, a general description of the arrangements and methods, which the Concessionaire proposes to adopt for the execution of the Works. e. The Project Implementation Schedule shall be developed using PERT (Programme Evaluation and Review Techniques) charts showing critical activities and milestones for completion of all works and services within the stipulated time period and submitted to Independent Engineer and the Authority.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Work Programmes. a. The Concessionaire shall prepare in consultation with the Independent Engineer and submit a Project Implementation Schedule to the Authority before the Compliance Date. The programme shall include the following: i) i. The order in which the Concessionaire proposes to carry out the Works, internal and external services (including each stage of design, procurement, manufacture, delivery to Project Site, construction, erection, testing and commissioning). ii) . All major events and activities in the production of Construction Documents. iii) . The particulars for the pre‐construction reviews and for any other submissions, approvals and consents specified in this Concession Agreement. b. Any alternation/ revision by the Concessionaire in the Project Implementation Schedule shall be made in accordance with Article 12.5. c. 12.3. If the progress of the Works does not conform to the Project Implementation Schedule, the Independent Engineer may instruct the Concessionaire to revise the Project Implementation Schedule, showing the modifications necessary to achieve completion as per Project Implementation Schedule. The Independent Engineer shall record the reasons for such revision of Project Implementation Schedule. d. c. The Concessionaire shall, whenever required by the Authority, provide in writing, for information, a general description of the arrangements and methods, which the Concessionaire proposes to adopt for the execution of the Works. e. d. The Project Implementation Schedule shall be developed using PERT (Programme Evaluation and Review Techniques) charts showing critical activities and milestones for milestones. For completion of all works and services within the stipulated time period and submitted to Independent Engineer and the Authority.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement